Курска киришүү · 3 мүн
ÖNORM B 2061 боюнча смета: K3, K7 жана кошумча чыгымдар боюнча доо
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Ойдон чыгарылган долбоор- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- ERPдеги иш
- Тапшырмалар: 5, болжол менен 3 саат 5 мүн
Ким кимге эмне берет
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сизге келет
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage lines1-тапшырма
- Wall item 03.01 without a price2-тапшырма
- Contract terms for the retentions4-тапшырма
- ÖBASite supervision, orders and checks
- Order for sound-insulating walls3-тапшырма
- Measured progress to end of August4-тапшырма
Сизден кетет
- Hourly rate on K3 and wage lines in the bill1-тапшырма
- K7 price with the surcharges on K22-тапшырма
- Additional-cost claim (Nachtrag)3-тапшырма
- Interim invoice (Abschlagsrechnung) with cover retention4-тапшырма
- Final invoice (Schlussrechnung) with warranty retention5-тапшырма
Долбоор боюнча жолуңуз
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
1-тапшырма · 30 мүн
K3: бригаданын саат баасы
- Натыйжа
- Hourly rate of the crew from K3, entered on the wage lines
- Документ
- K3 inputs and the bill (LV)
- ERPде
- Bill of Quantities
Build the price
2-тапшырма · 35 мүн
K7 жана K2: үстөктөр туура негизде
- Натыйжа
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Документ
- K2, K4 material price, time per m²
- ERPде
- Bill of Quantities
Price the change
3-тапшырма · 40 мүн
ÖNORM B 2110 боюнча кошумча чыгымдар боюнча доо
- Натыйжа
- New unit price and the additional cost, filed as a claim
- Документ
- The site supervisor's (ÖBA) order and the tender price basis
- ERPде
- Variations
Invoice
4-тапшырма · 40 мүн
Камсыздоо кармоосу менен ортоңку эсеп
- Натыйжа
- Interim invoice 1 and the amount payable
- Документ
- Measured progress and the contract terms
- ERPде
- Contracts
Invoice
5-тапшырма · 40 мүн
Акыркы эсеп жана кепилдик кармоосу
- Натыйжа
- Final invoice, warranty retention and the remaining payment
- Документ
- Contract sum, agreed claim, interim payment
- ERPде
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.