מבוא לקורס · 3 דק׳
תמחור לפי ÖNORM B 2061: K3, K7 ותביעה לעלויות נוספות
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
פרויקט בדיוני- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- עבודה ב-ERP
- 5 משימות, כ-3 ש׳ 5 דק׳
מי מעביר מה למי
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
מגיע אליכם
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesמשימה 1
- Wall item 03.01 without a priceמשימה 2
- Contract terms for the retentionsמשימה 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsמשימה 3
- Measured progress to end of Augustמשימה 4
יוצא מכם
- Hourly rate on K3 and wage lines in the billמשימה 1
- K7 price with the surcharges on K2משימה 2
- Additional-cost claim (Nachtrag)משימה 3
- Interim invoice (Abschlagsrechnung) with cover retentionמשימה 4
- Final invoice (Schlussrechnung) with warranty retentionמשימה 5
המסלול שלכם בפרויקט
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
משימה 1 · 30 דק׳
K3: תעריף השעה של הצוות
- התוצר שלכם
- Hourly rate of the crew from K3, entered on the wage lines
- מסמך
- K3 inputs and the bill (LV)
- ב-ERP
- Bill of Quantities
Build the price
משימה 2 · 35 דק׳
K7 ו-K2: תוספות על הבסיס הנכון
- התוצר שלכם
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- מסמך
- K2, K4 material price, time per m²
- ב-ERP
- Bill of Quantities
Price the change
משימה 3 · 40 דק׳
תביעה לעלויות נוספות לפי ÖNORM B 2110
- התוצר שלכם
- New unit price and the additional cost, filed as a claim
- מסמך
- The site supervisor's (ÖBA) order and the tender price basis
- ב-ERP
- Variations
Invoice
משימה 4 · 40 דק׳
חשבון ביניים עם עיכבון כיסוי (Deckungsrücklass)
- התוצר שלכם
- Interim invoice 1 and the amount payable
- מסמך
- Measured progress and the contract terms
- ב-ERP
- Contracts
Invoice
משימה 5 · 40 דק׳
חשבון סופי ועיכבון ליקויים
- התוצר שלכם
- Final invoice, warranty retention and the remaining payment
- מסמך
- Contract sum, agreed claim, interim payment
- ב-ERP
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
בכחול מה שהמשימה מוסיפה; באפור מה שעבר מהשלב הקודם.
בקצרה. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.