OpenConstruction Academy
Нэвтрэх / Бүртгүүлэх
MN

3-р даалгаврын өмнөх онол · 11 мин

A claim for additional cost under ÖNORM B 2110

ÖNORM B 2110 дагуух нэмэлт зардлын нэхэмжлэл

Энэ лекцийн дараа та дараахыг хийж чадна

  1. Decide whose sphere an ordered change falls into and when the claim must be notified.
  2. Derive a new unit price from the price bases of the bid, not from today's prices.
  3. Value the claim as (new price − old price) × quantity.
1 / 3

Whose sphere, and when to notify

ÖNORM B 2110, the Austrian standard contract conditions for building work, divides risk into spheres. The client's sphere includes its documents, its orders and materials it supplies (7.2.1); everything else is the contractor's, including its own calculation errors (7.2.2). When the client's site management (ÖBA) orders a change, the cost falls in the client's sphere. The contractor must notify the claim in principle before carrying out the work (7.3, 7.4.1). A late notice loses the claim as far as the client is put at a disadvantage by the delay.

Жишээ. Notify first, price second. A perfect price on a claim that was never notified may be worth nothing.
2 / 3

The new price continues the old calculation

The new unit price is built from the price bases of the bid and the time values of comparable items (7.4.2). The material is priced at the price list valid when the bid was made, not at today's offer: the contract price level stays, and price changes are a separate matter. Labour uses the time value of the comparable item and the bid's B21. Other costs carry the bid's overall surcharge.

Жишээ. Today's supplier price may be higher. Using it turns a change claim into a price-increase claim the contract does not grant.
3 / 3

The claim is the difference

The ordered work replaces an item already in the contract. The claim is the new price minus the contract price of the replaced item, times the quantity changed. The material price includes breakage and waste exactly as K4 would: quantity × price × (1 + breakage).

Жишээ. 12 bricks per m² at 6.10 € with 3 % breakage: 12 × 6.10 × 1.03 = 75.40 € per m².
Bricks per m²12
Price per brick, bid price list€6.10
With 3 % breakage€75.40

Price an ordered change of wall type

The ÖBA orders 120 m² of an internal wall to be built with a heavier brick. The contractor notified the claim the same day.

Масштабгүй
Бодлого
  • New brick: 12 per m² at €6.10 (price list at bid date), breakage 3 %. Today's supplier offer: €6.45.
  • Mortar 0.03 m³/m² at €148.00 per m³, waste 5 %. Comparable item: 1 h/m². B21 €56.34; overall surcharge 17.27 %.
  • Contract price of the replaced wall: €96.90 per m². Ordered quantity 120 m².
Алхам 1 / 3

Other costs per m²

Bricks and mortar at bid prices with breakage and waste, rounded. What are they?

12 × €6.10 × 1.03 + 0.03 × €148.00 × 1.05 = €79.75 per m².

Алхам 2 / 3

New unit price

Labour at B21 plus other costs with the surcharge. What is the new price?

1 × €56.34 + €79.75 × 1.1727 = €149.86 per m².

Contract price
€96.90
New price
€150 (€96.90 + €52.96)
Contract price
€96.90
New price
€150 (€96.90 + €52.96)
Алхам 3 / 3

Claim

(New price − contract price) × quantity. What is the claim, net?

(€149.86 − €96.90) × 120 = €6,355.20.

Товчхондоо. Notify before building. Then continue the bid's calculation: bid prices, comparable time values, the same surcharge. Claim the difference.

Өөрийгөө шалгах

Асуулт 1 / 3

A new item price is 140.00 €/m², the replaced contract item 112.50 €/m², the ordered quantity 80 m². What is the claim, net?

(140.00 − 112.50) × 80 = €2,200.00.
Асуулт 2 / 3

Which brick price goes into the new unit price?

  • That would turn a change into a price increase.

  • Right. The new price continues the bid's price bases.

  • No averaging; the bid's price basis applies.

Асуулт 3 / 3

The contractor builds the ordered wall and notifies the claim a month later. What follows under B 2110?

  • Notice in principle is required before the work.

  • Right.

  • There is no such rule.