OpenConstruction Academy
Logga in / Registrera
SV

Teori före uppgift 3 · 11 min

A claim for additional cost under ÖNORM B 2110

Krav på merkostnader (Mehrkostenforderung) enligt ÖNORM B 2110

Efter den här lektionen kan du

  1. Decide whose sphere an ordered change falls into and when the claim must be notified.
  2. Derive a new unit price from the price bases of the bid, not from today's prices.
  3. Value the claim as (new price − old price) × quantity.
1 / 3

Whose sphere, and when to notify

ÖNORM B 2110, the Austrian standard contract conditions for building work, divides risk into spheres. The client's sphere includes its documents, its orders and materials it supplies (7.2.1); everything else is the contractor's, including its own calculation errors (7.2.2). When the client's site management (ÖBA) orders a change, the cost falls in the client's sphere. The contractor must notify the claim in principle before carrying out the work (7.3, 7.4.1). A late notice loses the claim as far as the client is put at a disadvantage by the delay.

Exempel. Notify first, price second. A perfect price on a claim that was never notified may be worth nothing.
2 / 3

The new price continues the old calculation

The new unit price is built from the price bases of the bid and the time values of comparable items (7.4.2). The material is priced at the price list valid when the bid was made, not at today's offer: the contract price level stays, and price changes are a separate matter. Labour uses the time value of the comparable item and the bid's B21. Other costs carry the bid's overall surcharge.

Exempel. Today's supplier price may be higher. Using it turns a change claim into a price-increase claim the contract does not grant.
3 / 3

The claim is the difference

The ordered work replaces an item already in the contract. The claim is the new price minus the contract price of the replaced item, times the quantity changed. The material price includes breakage and waste exactly as K4 would: quantity × price × (1 + breakage).

Exempel. 12 bricks per m² at 6.10 € with 3 % breakage: 12 × 6.10 × 1.03 = 75.40 € per m².
Bricks per m²12
Price per brick, bid price list€6.10
With 3 % breakage€75.40

Price an ordered change of wall type

The ÖBA orders 120 m² of an internal wall to be built with a heavier brick. The contractor notified the claim the same day.

Inte skalenlig
Uppgiften
  • New brick: 12 per m² at €6.10 (price list at bid date), breakage 3 %. Today's supplier offer: €6.45.
  • Mortar 0.03 m³/m² at €148.00 per m³, waste 5 %. Comparable item: 1 h/m². B21 €56.34; overall surcharge 17.27 %.
  • Contract price of the replaced wall: €96.90 per m². Ordered quantity 120 m².
Steg 1 av 3

Other costs per m²

Bricks and mortar at bid prices with breakage and waste, rounded. What are they?

12 × €6.10 × 1.03 + 0.03 × €148.00 × 1.05 = €79.75 per m².

Steg 2 av 3

New unit price

Labour at B21 plus other costs with the surcharge. What is the new price?

1 × €56.34 + €79.75 × 1.1727 = €149.86 per m².

Contract price
€96.90
New price
€150 (€96.90 + €52.96)
Contract price
€96.90
New price
€150 (€96.90 + €52.96)
Steg 3 av 3

Claim

(New price − contract price) × quantity. What is the claim, net?

(€149.86 − €96.90) × 120 = €6,355.20.

Kort sagt. Notify before building. Then continue the bid's calculation: bid prices, comparable time values, the same surcharge. Claim the difference.

Testa dig själv

Fråga 1 av 3

A new item price is 140.00 €/m², the replaced contract item 112.50 €/m², the ordered quantity 80 m². What is the claim, net?

(140.00 − 112.50) × 80 = €2,200.00.
Fråga 2 av 3

Which brick price goes into the new unit price?

  • That would turn a change into a price increase.

  • Right. The new price continues the bid's price bases.

  • No averaging; the bid's price basis applies.

Fråga 3 av 3

The contractor builds the ordered wall and notifies the claim a month later. What follows under B 2110?

  • Notice in principle is required before the work.

  • Right.

  • There is no such rule.