OpenConstruction Academy
Нэвтрэх / Бүртгүүлэх
MN

4-р даалгаврын өмнөх онол · 12 мин

A change on the critical path: fragnet and time impact analysis

Критик замын захиалагчийн өөрчлөлт: фрагнет

Энэ лекцийн дараа та дараахыг хийж чадна

  1. Model a change as a fragnet: take out deleted work, add the new activity, link it where it sits.
  2. Measure the delay as the move of Substantial Completion on the current update.
  3. Convert a delay in working days into an extension in calendar days under A201-2017.
1 / 3

Time impact analysis in four moves

A prospective time impact analysis, as AACE International describes it in its recommended practice, measures a change before it is built. Take the current schedule update. Remove the work the change deletes. Insert a fragnet, a small network of the new work. Run the critical path and compare the finish with the finish before. The difference is the delay the change causes.

Жишээ. On a critical activity the deleted day comes off and the fragnet's days go on: the finish moves by 3 working days.
701-12+43734
  • 1 Planned length before
  • 2 Deleted work
  • 3 Fragnet
  • 4 Planned length after
2 / 3

Link the fragnet where the work sits

The links of a fragnet come from the building, not from convenience. Ask what physically has to be in place before the new work, and what cannot start until it is done. A fragnet hung beside the next activity, with nothing waiting for it, hides its own delay. The architect checks the logic, so put it on the change order backup.

Жишээ. Hung beside the next activity, the same change even shortens the job by the deleted day. That is the logic hiding the delay, not a saving.
Linked in series, as built
73
Hung beside the next activity
69
3 / 3

Working days to calendar days

The schedule measures the delay in working days. A201-2017 Section 8.1.4 makes a day in the Contract Documents a calendar day unless otherwise defined, so the Contract Time is adjusted in calendar days. Find the old and the new finish on a calendar and count the days between them, weekends included.

Жишээ. Six working days cross one weekend: the extension is 6 + 2 calendar days.
Substantial Completion beforeWednesday, March 31, 2027
Delay, working days6
Substantial Completion afterThursday, April 8, 2027
Extension, calendar days8

Lead-lined walls in two X-ray rooms

Another job, a medical office. The owner's change order replaces standard drywall in two X-ray rooms with lead-lined board.

Масштабгүй
Бодлого
  • Lead-lined board: 2,700 sq ft, the installer sets 360 sq ft a day.
  • Ground-floor drywall, 6 working days, is critical. The change deletes 1 day of standard board in it.
  • The board goes on after the drywall and before tape and finish.
  • Planned length before the change: 62. The next longest path: 57.
  • Substantial Completion before the change: Tuesday, March 2, 2027.
Lead-lined board, sq ft2,700
Output per day, sq ft360
Duration, working days?
Lead-lined board, sq ft2,700
Output per day, sq ft360
Duration, working days8
Алхам 1 / 4

Fragnet duration

What is the duration of the lead-lined board activity?

2,700 ÷ 360 = 7.5 days. Round up: 8 working days.

Алхам 2 / 4

Deleted work out first

What is the new duration of the ground-floor drywall?

6 − 1 = 5 working days. Left in, the deleted board would add a day the owner does not owe.

621-12+83?4
  • 1 Length before
  • 2 Standard board deleted
  • 3 Lead-lined fragnet
  • 4 Length after
621-12+83694
  • 1 Length before
  • 2 Standard board deleted
  • 3 Lead-lined fragnet
  • 4 Length after
Алхам 3 / 4

New planned length

The fragnet sits between drywall and tape and finish. What is the planned length now?

62 − 1 + 8 = 69, longer than the next path at 57. The delay is 69 − 62 working days.

Алхам 4 / 4

Extension in calendar days

Substantial Completion was Tuesday, March 2, 2027. What extension in calendar days does the change order state?

7 working days from Tuesday end on Thursday, March 11, 2027. One weekend lies between: 9 calendar days.

Товчхондоо. Take out what the change deletes, link the fragnet where the work sits, measure the move of the finish and state it in calendar days.

Өөрийгөө шалгах

Асуулт 1 / 3

A fragnet moves Substantial Completion by 5 working days. The old finish was Wednesday, March 3, 2027. What extension in calendar days does the change order state?

Five working days from a Wednesday end on the Wednesday a week later: 7 calendar days.
Асуулт 2 / 3

A change replaces vinyl flooring, already one day of the flooring activity, with sealed concrete. What comes first in the fragnet?

  • Right. Deleted work leaves the schedule first, or the analysis counts it twice.

  • The owner would pay for a day of work that no longer exists.

  • A fragnet goes where the work sits. Days at the end skip the logic and the float.

Асуулт 3 / 3

A new activity is added but nothing waits for it to finish. What does the analysis show?

  • Right. Without a successor the fragnet floats and hides its own delay.

  • Being in the schedule is not enough. The links decide what it moves.

  • With no successor nothing is pushed. Link it to what physically follows.