OpenConstruction Academy
Нэвтрэх / Бүртгүүлэх
MN

1-р даалгаврын өмнөх онол · 9 мин

A progress claim is a movement, not a total

Үнийн хуваариас гүйцэтгэлийн нэхэмжлэл 5

Сургалтын танилцуулга

Энэ лекцийн дараа та дараахыг хийж чадна

  1. Read a schedule of values the way the consultant certifies it: contract value × percent complete.
  2. Turn work done to date into the value for the period by taking off what was already certified.
  3. Say what an Ontario proper invoice must contain under the Construction Act, s. 6.1.
1 / 3

The schedule of values

On a stipulated price contract such as CCDC 2 - 2020 the contractor splits the contract price into divisions, each with a contract value. That split is the schedule of values. Every month the consultant agrees how far each division has gone, as a percent complete. Work done to date on a division is its contract value × that percent. Nobody re-measures quantities: the price is fixed, and the claim only says how much of it has been earned.

Жишээ. A division worth $640,000.00 that is 45 % complete has earned $288,000.00 to date.
Contract value of the division$640,000.00
Percent complete45%
Work done to date$288,000.00
2 / 3

Claim the movement only

The claim for the month is not the work done to date. Earlier claims have already been certified and paid, so each line claims to date less certified to date. Add the lines and you have the value of the claim. A division that has not moved claims nothing; a division the consultant marks back claims a negative amount, which reduces the claim. The balance still to be claimed is the contract price less work done to date, never less the claim alone.

Жишээ. To date $288,000.00, certified before $210,000.00: the line claims $78,000.00.
3 / 3

A proper invoice starts the clock

Ontario's Construction Act gives prompt payment rights only to a proper invoice. Section 6.1 lists what it must state: the contractor's name and address, the invoice date and the period it covers, the contract, a description of the work, the amount payable and the payment terms, and the name, title, mailing address and telephone number of the person to be paid, plus anything else the contract adds. Miss one item and the owner can say the payment clock never started.

Жишээ. An invoice without the period it covers is not a proper invoice, however right its figures are.

Claim the month on three divisions

A small clinic is built under CCDC 2 for a stipulated price made of three divisions. The consultant has agreed the percent complete at month end.

Масштабгүй
Бодлого
  • Mechanical: contract value $640,000.00, 45% complete, certified to date $210,000.00.
  • Electrical: contract value $380,000.00, 32% complete, certified to date $95,000.00.
  • Finishes: contract value $540,000.00, 12% complete, nothing certified yet.
  • The contract price is the sum of the three divisions.
Алхам 1 / 3

Mechanical line

Value × percent, less certified. What does the mechanical line claim?

$640,000.00 × 45% − $210,000.00 = $78,000.00.

Mechanical
$288,000 ($210,000 + $78,000)
Electrical
$121,600 ($95,000 + $26,600)
Finishes
$64,800
Mechanical
$288,000 ($210,000 + $78,000)
Electrical
$121,600 ($95,000 + $26,600)
Finishes
$64,800
Алхам 2 / 3

Value of the claim

Do the same for electrical and finishes and add the three lines. What is the claim, excluding HST?

$78,000.00 + ($380,000.00 × 32% − $95,000.00) + ($540,000.00 × 12% − $0.00) = $169,400.00.

Алхам 3 / 3

Still to be claimed

Contract price less work done to date. How much of the price is still to be claimed?

($640,000.00 + $380,000.00 + $540,000.00) − work done to date = $1,085,600.00.

Товчхондоо. Each line: value × percent complete − certified to date. The claim is the sum of the movements; the balance is the price less work done to date.

Өөрийгөө шалгах

Асуулт 1 / 3

A division worth $840,000.00 is 55 % complete; $365,000.00 has been certified on it. What does the line claim this month?

$840,000.00 × 55 % = $462,000.00 to date, less $365,000.00 certified = $97,000.00.
Асуулт 2 / 3

Last month a division was certified at 48 %. This month the consultant agrees 43 % after finding defective work. What does the line claim?

  • It can: the line follows the agreed percent, and the certified amount comes back.

  • Right. The movement is negative and reduces the claim.

  • That is work done to date. The claim is the movement.

Асуулт 3 / 3

Which of these makes a claim fail as a proper invoice under the Construction Act, s. 6.1?

  • The Act does not require paper. The contract may set the delivery method.

  • Right. The period is one of the listed contents.

  • A low claim is still a proper invoice.