Сургалтын танилцуулга · 3 мин
CCDC 2 гэрээгээр төлбөрөө хэрхэн авах вэ (Канад)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Зохиомол төсөл- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- ERP дээрх ажил
- Даалгавар: 5, ойролцоогоор 2 цаг 5 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- Firm of architectsConsultant, certifies
- Percent complete per divisionДаалгавар 1
- Directive 7: rock at gridline FДаалгавар 3
- Work left to complete or correctДаалгавар 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedДаалгавар 3
ТаProject accountant, general contractorТанаас гардаг
- Progress claim 5Даалгавар 1
- Amount payable now, HST inДаалгавар 2
- Change order 7Даалгавар 3
- Holdback releaseДаалгавар 5
- Their payment, by the Act's datesДаалгавар 4
Төсөл ба хүмүүс зохиомол. Хөрөг зургууд үүсгэгдсэн.
Төслөөр явах таны зам
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Даалгавар 1 · 25 мин
Үнийн хуваариас гүйцэтгэлийн нэхэмжлэл 5
- Үр дүн
- Progress claim 5, this month's movement per division
- Баримт бичиг
- Schedule of values with the agreed percent complete
- ERP дээр
- Contracts › Progress Claims
Claim
Даалгавар 2 · 25 мин
Барьцаа, HST болон үнэхээр төлөх дүн
- Үр дүн
- The holdback and the amount payable now, HST included
- Баримт бичиг
- The contract's holdback and HST terms
- ERP дээр
- Contracts
Change
Даалгавар 3 · 25 мин
Нэмэгдэлтэй өөрчлөлтийн захиалгын үнийг тогтоох
- Үр дүн
- Change order 7 (a priced change): cost plus two allowances
- Баримт бичиг
- Directive 7, own-forces cost and the sub's quote
- ERP дээр
- Variations
Get paid
Даалгавар 4 · 25 мин
Шуурхай төлбөрийн хуанли
- Үр дүн
- The payment deadlines and what the disputed division holds back
- Баримт бичиг
- The owner's notice of non-payment
- ERP дээр
- Contracts
Get paid
Даалгавар 5 · 25 мин
Мэдэгдэхүйц гүйцэтгэл ба барьцааг чөлөөлөх
- Үр дүн
- The substantial performance test (is the job essentially done?) and the holdback release
- Баримт бичиг
- Estimate of the work left to do
- ERP дээр
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.