Сургалтын танилцуулга · 3 мин

CCDC 2 гэрээгээр төлбөрөө хэрхэн авах вэ (Канад)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

1-р даалгаврыг эхлэх

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Зохиомол төсөл
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 2 цаг 5 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionДаалгавар 1
    • Directive 7: rock at gridline FДаалгавар 3
    • Work left to complete or correctДаалгавар 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedДаалгавар 3
ТаProject accountant, general contractor

Танаас гардаг

    • Progress claim 5Даалгавар 1
    • Amount payable now, HST inДаалгавар 2
    • Change order 7Даалгавар 3
    • Holdback releaseДаалгавар 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesДаалгавар 4
    Your subcontractorsPaid after you are paid

Төсөл ба хүмүүс зохиомол. Хөрөг зургууд үүсгэгдсэн.

Төслөөр явах таны зам

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Даалгавар 1 · 25 мин

    Үнийн хуваариас гүйцэтгэлийн нэхэмжлэл 5

    Үр дүн
    Progress claim 5, this month's movement per division
    Баримт бичиг
    Schedule of values with the agreed percent complete
    ERP дээр
    Contracts › Progress Claims
  2. Claim

    Даалгавар 2 · 25 мин

    Барьцаа, HST болон үнэхээр төлөх дүн

    Үр дүн
    The holdback and the amount payable now, HST included
    Баримт бичиг
    The contract's holdback and HST terms
    ERP дээр
    Contracts
  3. Change

    Даалгавар 3 · 25 мин

    Нэмэгдэлтэй өөрчлөлтийн захиалгын үнийг тогтоох

    Үр дүн
    Change order 7 (a priced change): cost plus two allowances
    Баримт бичиг
    Directive 7, own-forces cost and the sub's quote
    ERP дээр
    Variations
  4. Get paid

    Даалгавар 4 · 25 мин

    Шуурхай төлбөрийн хуанли

    Үр дүн
    The payment deadlines and what the disputed division holds back
    Баримт бичиг
    The owner's notice of non-payment
    ERP дээр
    Contracts
  5. Get paid

    Даалгавар 5 · 25 мин

    Мэдэгдэхүйц гүйцэтгэл ба барьцааг чөлөөлөх

    Үр дүн
    The substantial performance test (is the job essentially done?) and the holdback release
    Баримт бичиг
    Estimate of the work left to do
    ERP дээр
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Даалгавар 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Даалгавар 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Даалгавар 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Даалгавар 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.