Курсқа кіріспе · 3 мин

CCDC 2 келісімшарты бойынша төлем алу (Канада)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

1-тапсырманы бастау

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Ойдан шығарылған жоба
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
ERP-дегі жұмыс
Тапсырмалар: 5, шамамен 2 сағ 5 мин

Кім кімге не береді

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сізге келеді

  • Firm of architectsConsultant, certifies
    • Percent complete per division1-тапсырма
    • Directive 7: rock at gridline F3-тапсырма
    • Work left to complete or correct5-тапсырма
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup included3-тапсырма
СізProject accountant, general contractor

Сізден кетеді

    • Progress claim 51-тапсырма
    • Amount payable now, HST in2-тапсырма
    • Change order 73-тапсырма
    • Holdback release5-тапсырма
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's dates4-тапсырма
    Your subcontractorsPaid after you are paid

Жоба мен адамдар ойдан шығарылған. Портреттер генерацияланған.

Жоба бойынша жолыңыз

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    1-тапсырма · 25 мин

    Жұмыс құнының кестесі бойынша 5-орындалған жұмыстар талабы

    Нәтиже
    Progress claim 5, this month's movement per division
    Құжат
    Schedule of values with the agreed percent complete
    ERP-де
    Contracts › Progress Claims
  2. Claim

    2-тапсырма · 25 мин

    Ұстап қалу, HST және шын мәнінде төленетін сома

    Нәтиже
    The holdback and the amount payable now, HST included
    Құжат
    The contract's holdback and HST terms
    ERP-де
    Contracts
  3. Change

    3-тапсырма · 25 мин

    Үстемелері бар өзгерістер туралы бұйрықтың бағасын қою

    Нәтиже
    Change order 7 (a priced change): cost plus two allowances
    Құжат
    Directive 7, own-forces cost and the sub's quote
    ERP-де
    Variations
  4. Get paid

    4-тапсырма · 25 мин

    Уақтылы төлем күнтізбесі

    Нәтиже
    The payment deadlines and what the disputed division holds back
    Құжат
    The owner's notice of non-payment
    ERP-де
    Contracts
  5. Get paid

    5-тапсырма · 25 мин

    Елеулі аяқталу және ұсталған соманы қайтару

    Нәтиже
    The substantial performance test (is the job essentially done?) and the holdback release
    Құжат
    Estimate of the work left to do
    ERP-де
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
1-тапсырмаMovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
2-тапсырмаHoldback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
4-тапсырмаDisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
5-тапсырмаReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Көкпен — тапсырма қосатын бөлік; сұрмен — алдыңғы қадамнан келгені.

Қысқаша. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.