Kursuse sissejuhatus · 3 min

Kuidas saada tasu CCDC 2 lepingu alusel (Kanada)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

Alusta ülesannet 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Väljamõeldud projekt
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
Töö ERP-s
Ülesandeid 5, umbes 2 h 5 min

Kes annab kellele mida

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tuleb sinule

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionÜlesanne 1
    • Directive 7: rock at gridline FÜlesanne 3
    • Work left to complete or correctÜlesanne 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedÜlesanne 3
SinaProject accountant, general contractor

Läheb sinult

    • Progress claim 5Ülesanne 1
    • Amount payable now, HST inÜlesanne 2
    • Change order 7Ülesanne 3
    • Holdback releaseÜlesanne 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesÜlesanne 4
    Your subcontractorsPaid after you are paid

Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.

Sinu tee läbi projekti

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Ülesanne 1 · 25 min

    Maksenõue 5 tööde maksumuse jaotuse alusel

    Sinu tulemus
    Progress claim 5, this month's movement per division
    Dokument
    Schedule of values with the agreed percent complete
    ERP-s
    Contracts › Progress Claims
  2. Claim

    Ülesanne 2 · 25 min

    Pidatis, HST ja mis tegelikult makstakse

    Sinu tulemus
    The holdback and the amount payable now, HST included
    Dokument
    The contract's holdback and HST terms
    ERP-s
    Contracts
  3. Change

    Ülesanne 3 · 25 min

    Muudatuskorralduse hindamine juurdehindlustega

    Sinu tulemus
    Change order 7 (a priced change): cost plus two allowances
    Dokument
    Directive 7, own-forces cost and the sub's quote
    ERP-s
    Variations
  4. Get paid

    Ülesanne 4 · 25 min

    Õigeaegse maksmise kalender

    Sinu tulemus
    The payment deadlines and what the disputed division holds back
    Dokument
    The owner's notice of non-payment
    ERP-s
    Contracts
  5. Get paid

    Ülesanne 5 · 25 min

    Oluline täitmine ja pidatise vabastamine

    Sinu tulemus
    The substantial performance test (is the job essentially done?) and the holdback release
    Dokument
    Estimate of the work left to do
    ERP-s
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Ülesanne 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Ülesanne 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Ülesanne 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Ülesanne 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Sinine on see, mida ülesanne lisab; hall tuleb varasemast.

Lühidalt. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.