Kursuse sissejuhatus · 3 min
Kuidas saada tasu CCDC 2 lepingu alusel (Kanada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Väljamõeldud projekt- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Töö ERP-s
- Ülesandeid 5, umbes 2 h 5 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- Firm of architectsConsultant, certifies
- Percent complete per divisionÜlesanne 1
- Directive 7: rock at gridline FÜlesanne 3
- Work left to complete or correctÜlesanne 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedÜlesanne 3
SinaProject accountant, general contractorLäheb sinult
- Progress claim 5Ülesanne 1
- Amount payable now, HST inÜlesanne 2
- Change order 7Ülesanne 3
- Holdback releaseÜlesanne 5
- Their payment, by the Act's datesÜlesanne 4
Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.
Sinu tee läbi projekti
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Ülesanne 1 · 25 min
Maksenõue 5 tööde maksumuse jaotuse alusel
- Sinu tulemus
- Progress claim 5, this month's movement per division
- Dokument
- Schedule of values with the agreed percent complete
- ERP-s
- Contracts › Progress Claims
Claim
Ülesanne 2 · 25 min
Pidatis, HST ja mis tegelikult makstakse
- Sinu tulemus
- The holdback and the amount payable now, HST included
- Dokument
- The contract's holdback and HST terms
- ERP-s
- Contracts
Change
Ülesanne 3 · 25 min
Muudatuskorralduse hindamine juurdehindlustega
- Sinu tulemus
- Change order 7 (a priced change): cost plus two allowances
- Dokument
- Directive 7, own-forces cost and the sub's quote
- ERP-s
- Variations
Get paid
Ülesanne 4 · 25 min
Õigeaegse maksmise kalender
- Sinu tulemus
- The payment deadlines and what the disputed division holds back
- Dokument
- The owner's notice of non-payment
- ERP-s
- Contracts
Get paid
Ülesanne 5 · 25 min
Oluline täitmine ja pidatise vabastamine
- Sinu tulemus
- The substantial performance test (is the job essentially done?) and the holdback release
- Dokument
- Estimate of the work left to do
- ERP-s
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.