Introduksjon til kurset · 3 min
Få betalt på en CCDC 2-kontrakt (Canada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Fiktivt prosjekt- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Arbeid i ERP
- 5 oppgaver, omtrent 2 t 5 min
Hvem gir hva til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til deg
- Firm of architectsConsultant, certifies
- Percent complete per divisionOppgave 1
- Directive 7: rock at gridline FOppgave 3
- Work left to complete or correctOppgave 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedOppgave 3
DuProject accountant, general contractorGår fra deg
- Progress claim 5Oppgave 1
- Amount payable now, HST inOppgave 2
- Change order 7Oppgave 3
- Holdback releaseOppgave 5
- Their payment, by the Act's datesOppgave 4
Prosjektet og personene er fiktive. Portrettene er genererte.
Din vei gjennom prosjektet
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Oppgave 1 · 25 min
Betalingskrav 5 ut fra verdiplanen
- Du leverer
- Progress claim 5, this month's movement per division
- Dokument
- Schedule of values with the agreed percent complete
- I ERP
- Contracts › Progress Claims
Claim
Oppgave 2 · 25 min
Tilbakehold, HST og hva som faktisk skal betales
- Du leverer
- The holdback and the amount payable now, HST included
- Dokument
- The contract's holdback and HST terms
- I ERP
- Contracts
Change
Oppgave 3 · 25 min
Prisfastsett en endringsordre med påslag
- Du leverer
- Change order 7 (a priced change): cost plus two allowances
- Dokument
- Directive 7, own-forces cost and the sub's quote
- I ERP
- Variations
Get paid
Oppgave 4 · 25 min
Kalenderen for rask betaling
- Du leverer
- The payment deadlines and what the disputed division holds back
- Dokument
- The owner's notice of non-payment
- I ERP
- Contracts
Get paid
Oppgave 5 · 25 min
Vesentlig ferdigstillelse og frigivelse av tilbakeholdet
- Du leverer
- The substantial performance test (is the job essentially done?) and the holdback release
- Dokument
- Estimate of the work left to do
- I ERP
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Blått er det oppgaven legger til; grått er overført fra før.
Kort sagt. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.