Panimula ng kurso · 3 min
Ang mabayaran sa ilalim ng kontratang CCDC 2 (Canada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Kathang-isip na proyekto- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Trabaho sa ERP
- 5 gawain, mga 2 oras 5 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- Firm of architectsConsultant, certifies
- Percent complete per divisionGawain 1
- Directive 7: rock at gridline FGawain 3
- Work left to complete or correctGawain 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedGawain 3
IkawProject accountant, general contractorLumalabas sa iyo
- Progress claim 5Gawain 1
- Amount payable now, HST inGawain 2
- Change order 7Gawain 3
- Holdback releaseGawain 5
- Their payment, by the Act's datesGawain 4
Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.
Ang ruta mo sa proyekto
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Gawain 1 · 25 min
Progress claim 5 mula sa iskedyul ng halaga ng trabaho
- Ang gagawin mo
- Progress claim 5, this month's movement per division
- Dokumento
- Schedule of values with the agreed percent complete
- Sa ERP
- Contracts › Progress Claims
Claim
Gawain 2 · 25 min
Holdback, HST, at ang halagang talagang babayaran
- Ang gagawin mo
- The holdback and the amount payable now, HST included
- Dokumento
- The contract's holdback and HST terms
- Sa ERP
- Contracts
Change
Gawain 3 · 25 min
Pagtatakda ng presyo ng change order na may porsyento ng dagdag
- Ang gagawin mo
- Change order 7 (a priced change): cost plus two allowances
- Dokumento
- Directive 7, own-forces cost and the sub's quote
- Sa ERP
- Variations
Get paid
Gawain 4 · 25 min
Kalendaryo ng agarang pagbabayad
- Ang gagawin mo
- The payment deadlines and what the disputed division holds back
- Dokumento
- The owner's notice of non-payment
- Sa ERP
- Contracts
Get paid
Gawain 5 · 25 min
Substantial performance at paglalabas ng holdback
- Ang gagawin mo
- The substantial performance test (is the job essentially done?) and the holdback release
- Dokumento
- Estimate of the work left to do
- Sa ERP
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.