You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

Simulan ang gawain 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Kathang-isip na proyekto
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
Trabaho sa ERP
5 gawain, mga 2 oras 5 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionGawain 1
    • Directive 7: rock at gridline FGawain 3
    • Work left to complete or correctGawain 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedGawain 3
IkawProject accountant, general contractor

Lumalabas sa iyo

    • Progress claim 5Gawain 1
    • Amount payable now, HST inGawain 2
    • Change order 7Gawain 3
    • Holdback releaseGawain 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesGawain 4
    Your subcontractorsPaid after you are paid

Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.

Ang ruta mo sa proyekto

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Gawain 1 · 25 min

    Progress claim 5 mula sa iskedyul ng halaga ng trabaho

    Ang gagawin mo
    Progress claim 5, this month's movement per division
    Dokumento
    Schedule of values with the agreed percent complete
    Sa ERP
    Contracts › Progress Claims
  2. Claim

    Gawain 2 · 25 min

    Holdback, HST, at ang halagang talagang babayaran

    Ang gagawin mo
    The holdback and the amount payable now, HST included
    Dokumento
    The contract's holdback and HST terms
    Sa ERP
    Contracts
  3. Change

    Gawain 3 · 25 min

    Pagtatakda ng presyo ng change order na may porsyento ng dagdag

    Ang gagawin mo
    Change order 7 (a priced change): cost plus two allowances
    Dokumento
    Directive 7, own-forces cost and the sub's quote
    Sa ERP
    Variations
  4. Get paid

    Gawain 4 · 25 min

    Kalendaryo ng agarang pagbabayad

    Ang gagawin mo
    The payment deadlines and what the disputed division holds back
    Dokumento
    The owner's notice of non-payment
    Sa ERP
    Contracts
  5. Get paid

    Gawain 5 · 25 min

    Substantial performance at paglalabas ng holdback

    Ang gagawin mo
    The substantial performance test (is the job essentially done?) and the holdback release
    Dokumento
    Estimate of the work left to do
    Sa ERP
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Gawain 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Gawain 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Gawain 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Gawain 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.