OpenConstruction Academy
התחברות / הרשמה
HE

מבוא לקורס · 3 דק׳

איך מקבלים תשלום בחוזה CCDC 2 (קנדה)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

התחלת משימה 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.פרויקט בדיוני
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
עבודה ב-ERP
5 משימות, כ-2 ש׳ 5 דק׳

מי מעביר מה למי

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

מגיע אליכם

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionמשימה 1
    • Directive 7: rock at gridline Fמשימה 3
    • Work left to complete or correctמשימה 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedמשימה 3
אתםProject accountant, general contractor

יוצא מכם

    • Progress claim 5משימה 1
    • Amount payable now, HST inמשימה 2
    • Change order 7משימה 3
    • Holdback releaseמשימה 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesמשימה 4
    Your subcontractorsPaid after you are paid

הפרויקט והאנשים בדיוניים. הדיוקנאות נוצרו בתוכנה.

המסלול שלכם בפרויקט

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    משימה 1 · 25 דק׳

    חשבון חלקי מספר 5 מתוך כתב הכמויות והערכים

    התוצר שלכם
    Progress claim 5, this month's movement per division
    מסמך
    Schedule of values with the agreed percent complete
    ב-ERP
    Contracts › Progress Claims
  2. Claim

    משימה 2 · 25 דק׳

    הסכום הנעצר, HST ומה שמגיע בפועל לתשלום

    התוצר שלכם
    The holdback and the amount payable now, HST included
    מסמך
    The contract's holdback and HST terms
    ב-ERP
    Contracts
  3. Change

    משימה 3 · 25 דק׳

    תמחור הוראת שינוי עם תוספות

    התוצר שלכם
    Change order 7 (a priced change): cost plus two allowances
    מסמך
    Directive 7, own-forces cost and the sub's quote
    ב-ERP
    Variations
  4. Get paid

    משימה 4 · 25 דק׳

    לוח הזמנים של תשלום מהיר

    התוצר שלכם
    The payment deadlines and what the disputed division holds back
    מסמך
    The owner's notice of non-payment
    ב-ERP
    Contracts
  5. Get paid

    משימה 5 · 25 דק׳

    השלמה מהותית ושחרור הסכום הנעצר

    התוצר שלכם
    The substantial performance test (is the job essentially done?) and the holdback release
    מסמך
    Estimate of the work left to do
    ב-ERP
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
משימה 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
משימה 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
משימה 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
משימה 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

בכחול מה שהמשימה מוסיפה; באפור מה שעבר מהשלב הקודם.

בקצרה. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.