Course introduction · 3 min
Get paid under a CCDC 2 contract (Canada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Fictional project- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Work in the ERP
- 5 tasks, about 2 h 5 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Firm of architectsConsultant, certifies
- Percent complete per divisionTask 1
- Directive 7: rock at gridline FTask 3
- Work left to complete or correctTask 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedTask 3
YouProject accountant, general contractorGoes from you
- Progress claim 5Task 1
- Amount payable now, HST inTask 2
- Change order 7Task 3
- Holdback releaseTask 5
- Their payment, by the Act's datesTask 4
The project and the people are fictional. Portraits are generated.
Your route through the job
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Task 1 · 25 min
Progress claim 5 from the schedule of values
- You produce
- Progress claim 5, this month's movement per division
- Document
- Schedule of values with the agreed percent complete
- In the ERP
- Contracts › Progress Claims
Claim
Task 2 · 25 min
Holdback, HST and what is actually payable
- You produce
- The holdback and the amount payable now, HST included
- Document
- The contract's holdback and HST terms
- In the ERP
- Contracts
Change
Task 3 · 25 min
Price a change order with markups
- You produce
- Change order 7 (a priced change): cost plus two allowances
- Document
- Directive 7, own-forces cost and the sub's quote
- In the ERP
- Variations
Get paid
Task 4 · 25 min
The prompt payment calendar
- You produce
- The payment deadlines and what the disputed division holds back
- Document
- The owner's notice of non-payment
- In the ERP
- Contracts
Get paid
Task 5 · 25 min
Substantial performance and the holdback release
- You produce
- The substantial performance test (is the job essentially done?) and the holdback release
- Document
- Estimate of the work left to do
- In the ERP
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Blue is what the task adds; grey is carried over from before.
In short. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.