Course introduction · 3 min

Get paid under a CCDC 2 contract (Canada)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

Start task 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Fictional project
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
Work in the ERP
5 tasks, about 2 h 5 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionTask 1
    • Directive 7: rock at gridline FTask 3
    • Work left to complete or correctTask 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedTask 3
YouProject accountant, general contractor

Goes from you

    • Progress claim 5Task 1
    • Amount payable now, HST inTask 2
    • Change order 7Task 3
    • Holdback releaseTask 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesTask 4
    Your subcontractorsPaid after you are paid

The project and the people are fictional. Portraits are generated.

Your route through the job

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Task 1 · 25 min

    Progress claim 5 from the schedule of values

    You produce
    Progress claim 5, this month's movement per division
    Document
    Schedule of values with the agreed percent complete
    In the ERP
    Contracts › Progress Claims
  2. Claim

    Task 2 · 25 min

    Holdback, HST and what is actually payable

    You produce
    The holdback and the amount payable now, HST included
    Document
    The contract's holdback and HST terms
    In the ERP
    Contracts
  3. Change

    Task 3 · 25 min

    Price a change order with markups

    You produce
    Change order 7 (a priced change): cost plus two allowances
    Document
    Directive 7, own-forces cost and the sub's quote
    In the ERP
    Variations
  4. Get paid

    Task 4 · 25 min

    The prompt payment calendar

    You produce
    The payment deadlines and what the disputed division holds back
    Document
    The owner's notice of non-payment
    In the ERP
    Contracts
  5. Get paid

    Task 5 · 25 min

    Substantial performance and the holdback release

    You produce
    The substantial performance test (is the job essentially done?) and the holdback release
    Document
    Estimate of the work left to do
    In the ERP
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Task 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Task 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Task 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Task 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Blue is what the task adds; grey is carried over from before.

In short. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.