Въведение в курса · 3 мин
Как да получите плащане по договор CCDC 2 (Канада)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Измислен проект- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Работа в ERP
- Задачи: 5, около 2 ч 5 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- Firm of architectsConsultant, certifies
- Percent complete per divisionЗадача 1
- Directive 7: rock at gridline FЗадача 3
- Work left to complete or correctЗадача 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedЗадача 3
ВиеProject accountant, general contractorТръгва от вас
- Progress claim 5Задача 1
- Amount payable now, HST inЗадача 2
- Change order 7Задача 3
- Holdback releaseЗадача 5
- Their payment, by the Act's datesЗадача 4
Проектът и хората са измислени. Портретите са генерирани.
Вашият път през проекта
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Задача 1 · 25 мин
Искане за междинно плащане 5 по ведомостта на стойностите
- Вашият резултат
- Progress claim 5, this month's movement per division
- Документ
- Schedule of values with the agreed percent complete
- В ERP
- Contracts › Progress Claims
Claim
Задача 2 · 25 мин
Гаранционно задържане, HST и какво наистина се плаща
- Вашият резултат
- The holdback and the amount payable now, HST included
- Документ
- The contract's holdback and HST terms
- В ERP
- Contracts
Change
Задача 3 · 25 мин
Остойностяване на заповед за промяна с надбавки
- Вашият резултат
- Change order 7 (a priced change): cost plus two allowances
- Документ
- Directive 7, own-forces cost and the sub's quote
- В ERP
- Variations
Get paid
Задача 4 · 25 мин
Календар на бързото плащане
- Вашият резултат
- The payment deadlines and what the disputed division holds back
- Документ
- The owner's notice of non-payment
- В ERP
- Contracts
Get paid
Задача 5 · 25 мин
Съществено завършване и освобождаване на гаранционното задържане
- Вашият резултат
- The substantial performance test (is the job essentially done?) and the holdback release
- Документ
- Estimate of the work left to do
- В ERP
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.