OpenConstruction Academy
Вход / Регистрация
BG

Въведение в курса · 3 мин

Как да получите плащане по договор CCDC 2 (Канада)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

Започнете задача 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Измислен проект
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
Работа в ERP
Задачи: 5, около 2 ч 5 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionЗадача 1
    • Directive 7: rock at gridline FЗадача 3
    • Work left to complete or correctЗадача 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedЗадача 3
ВиеProject accountant, general contractor

Тръгва от вас

    • Progress claim 5Задача 1
    • Amount payable now, HST inЗадача 2
    • Change order 7Задача 3
    • Holdback releaseЗадача 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesЗадача 4
    Your subcontractorsPaid after you are paid

Проектът и хората са измислени. Портретите са генерирани.

Вашият път през проекта

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Задача 1 · 25 мин

    Искане за междинно плащане 5 по ведомостта на стойностите

    Вашият резултат
    Progress claim 5, this month's movement per division
    Документ
    Schedule of values with the agreed percent complete
    В ERP
    Contracts › Progress Claims
  2. Claim

    Задача 2 · 25 мин

    Гаранционно задържане, HST и какво наистина се плаща

    Вашият резултат
    The holdback and the amount payable now, HST included
    Документ
    The contract's holdback and HST terms
    В ERP
    Contracts
  3. Change

    Задача 3 · 25 мин

    Остойностяване на заповед за промяна с надбавки

    Вашият резултат
    Change order 7 (a priced change): cost plus two allowances
    Документ
    Directive 7, own-forces cost and the sub's quote
    В ERP
    Variations
  4. Get paid

    Задача 4 · 25 мин

    Календар на бързото плащане

    Вашият резултат
    The payment deadlines and what the disputed division holds back
    Документ
    The owner's notice of non-payment
    В ERP
    Contracts
  5. Get paid

    Задача 5 · 25 мин

    Съществено завършване и освобождаване на гаранционното задържане

    Вашият резултат
    The substantial performance test (is the job essentially done?) and the holdback release
    Документ
    Estimate of the work left to do
    В ERP
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Задача 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Задача 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Задача 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Задача 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.