Inleiding tot de cursus · 3 min

Uitbetaald krijgen op een CCDC 2-contract (Canada)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

Start opdracht 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Fictief project
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
Werk in de ERP
5 opdrachten, ongeveer 2 u 5 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionOpdracht 1
    • Directive 7: rock at gridline FOpdracht 3
    • Work left to complete or correctOpdracht 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedOpdracht 3
UProject accountant, general contractor

Gaat van u uit

    • Progress claim 5Opdracht 1
    • Amount payable now, HST inOpdracht 2
    • Change order 7Opdracht 3
    • Holdback releaseOpdracht 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesOpdracht 4
    Your subcontractorsPaid after you are paid

Het project en de mensen zijn fictief. De portretten zijn gegenereerd.

Uw route door het project

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Opdracht 1 · 25 min

    Voortgangsdeclaratie 5 uit de waardeverdelingsstaat

    U levert
    Progress claim 5, this month's movement per division
    Document
    Schedule of values with the agreed percent complete
    In de ERP
    Contracts › Progress Claims
  2. Claim

    Opdracht 2 · 25 min

    Inhouding, HST en wat er werkelijk te betalen is

    U levert
    The holdback and the amount payable now, HST included
    Document
    The contract's holdback and HST terms
    In de ERP
    Contracts
  3. Change

    Opdracht 3 · 25 min

    Een meerwerkopdracht prijzen met opslagen

    U levert
    Change order 7 (a priced change): cost plus two allowances
    Document
    Directive 7, own-forces cost and the sub's quote
    In de ERP
    Variations
  4. Get paid

    Opdracht 4 · 25 min

    De kalender voor snelle betaling

    U levert
    The payment deadlines and what the disputed division holds back
    Document
    The owner's notice of non-payment
    In de ERP
    Contracts
  5. Get paid

    Opdracht 5 · 25 min

    Substantiële voltooiing en de vrijgave van de inhouding

    U levert
    The substantial performance test (is the job essentially done?) and the holdback release
    Document
    Estimate of the work left to do
    In de ERP
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Opdracht 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Opdracht 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Opdracht 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Opdracht 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.