Inleiding tot de cursus · 3 min
Uitbetaald krijgen op een CCDC 2-contract (Canada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Fictief project- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Werk in de ERP
- 5 opdrachten, ongeveer 2 u 5 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
- Firm of architectsConsultant, certifies
- Percent complete per divisionOpdracht 1
- Directive 7: rock at gridline FOpdracht 3
- Work left to complete or correctOpdracht 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedOpdracht 3
UProject accountant, general contractorGaat van u uit
- Progress claim 5Opdracht 1
- Amount payable now, HST inOpdracht 2
- Change order 7Opdracht 3
- Holdback releaseOpdracht 5
- Their payment, by the Act's datesOpdracht 4
Het project en de mensen zijn fictief. De portretten zijn gegenereerd.
Uw route door het project
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Opdracht 1 · 25 min
Voortgangsdeclaratie 5 uit de waardeverdelingsstaat
- U levert
- Progress claim 5, this month's movement per division
- Document
- Schedule of values with the agreed percent complete
- In de ERP
- Contracts › Progress Claims
Claim
Opdracht 2 · 25 min
Inhouding, HST en wat er werkelijk te betalen is
- U levert
- The holdback and the amount payable now, HST included
- Document
- The contract's holdback and HST terms
- In de ERP
- Contracts
Change
Opdracht 3 · 25 min
Een meerwerkopdracht prijzen met opslagen
- U levert
- Change order 7 (a priced change): cost plus two allowances
- Document
- Directive 7, own-forces cost and the sub's quote
- In de ERP
- Variations
Get paid
Opdracht 4 · 25 min
De kalender voor snelle betaling
- U levert
- The payment deadlines and what the disputed division holds back
- Document
- The owner's notice of non-payment
- In de ERP
- Contracts
Get paid
Opdracht 5 · 25 min
Substantiële voltooiing en de vrijgave van de inhouding
- U levert
- The substantial performance test (is the job essentially done?) and the holdback release
- Document
- Estimate of the work left to do
- In de ERP
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.