You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

1-тапшырманы баштоо

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Ойдон чыгарылган долбоор
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
ERPдеги иш
Тапшырмалар: 5, болжол менен 2 саат 5 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • Firm of architectsConsultant, certifies
    • Percent complete per division1-тапшырма
    • Directive 7: rock at gridline F3-тапшырма
    • Work left to complete or correct5-тапшырма
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup included3-тапшырма
СизProject accountant, general contractor

Сизден кетет

    • Progress claim 51-тапшырма
    • Amount payable now, HST in2-тапшырма
    • Change order 73-тапшырма
    • Holdback release5-тапшырма
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's dates4-тапшырма
    Your subcontractorsPaid after you are paid

Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.

Долбоор боюнча жолуңуз

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    1-тапшырма · 25 мүн

    Иштердин наркынын тизмеги боюнча 5-аткарылган иштер талабы

    Натыйжа
    Progress claim 5, this month's movement per division
    Документ
    Schedule of values with the agreed percent complete
    ERPде
    Contracts › Progress Claims
  2. Claim

    2-тапшырма · 25 мүн

    Кармоо, HST жана чындыгында төлөнүүчү сумма

    Натыйжа
    The holdback and the amount payable now, HST included
    Документ
    The contract's holdback and HST terms
    ERPде
    Contracts
  3. Change

    3-тапшырма · 25 мүн

    Үстөмөлөрү бар өзгөртүү буйругунун баасын коюу

    Натыйжа
    Change order 7 (a priced change): cost plus two allowances
    Документ
    Directive 7, own-forces cost and the sub's quote
    ERPде
    Variations
  4. Get paid

    4-тапшырма · 25 мүн

    Өз убагындагы төлөм календары

    Натыйжа
    The payment deadlines and what the disputed division holds back
    Документ
    The owner's notice of non-payment
    ERPде
    Contracts
  5. Get paid

    5-тапшырма · 25 мүн

    Олуттуу аяктоо жана кармалган сумманы кайтаруу

    Натыйжа
    The substantial performance test (is the job essentially done?) and the holdback release
    Документ
    Estimate of the work left to do
    ERPде
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
1-тапшырмаMovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
2-тапшырмаHoldback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
4-тапшырмаDisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
5-тапшырмаReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.