Курска киришүү · 3 мүн
CCDC 2 келишими боюнча төлөм алуу (Канада)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Ойдон чыгарылган долбоор- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- ERPдеги иш
- Тапшырмалар: 5, болжол менен 2 саат 5 мүн
Ким кимге эмне берет
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сизге келет
- Firm of architectsConsultant, certifies
- Percent complete per division1-тапшырма
- Directive 7: rock at gridline F3-тапшырма
- Work left to complete or correct5-тапшырма
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup included3-тапшырма
СизProject accountant, general contractorСизден кетет
- Progress claim 51-тапшырма
- Amount payable now, HST in2-тапшырма
- Change order 73-тапшырма
- Holdback release5-тапшырма
- Their payment, by the Act's dates4-тапшырма
Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.
Долбоор боюнча жолуңуз
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
1-тапшырма · 25 мүн
Иштердин наркынын тизмеги боюнча 5-аткарылган иштер талабы
- Натыйжа
- Progress claim 5, this month's movement per division
- Документ
- Schedule of values with the agreed percent complete
- ERPде
- Contracts › Progress Claims
Claim
2-тапшырма · 25 мүн
Кармоо, HST жана чындыгында төлөнүүчү сумма
- Натыйжа
- The holdback and the amount payable now, HST included
- Документ
- The contract's holdback and HST terms
- ERPде
- Contracts
Change
3-тапшырма · 25 мүн
Үстөмөлөрү бар өзгөртүү буйругунун баасын коюу
- Натыйжа
- Change order 7 (a priced change): cost plus two allowances
- Документ
- Directive 7, own-forces cost and the sub's quote
- ERPде
- Variations
Get paid
4-тапшырма · 25 мүн
Өз убагындагы төлөм календары
- Натыйжа
- The payment deadlines and what the disputed division holds back
- Документ
- The owner's notice of non-payment
- ERPде
- Contracts
Get paid
5-тапшырма · 25 мүн
Олуттуу аяктоо жана кармалган сумманы кайтаруу
- Натыйжа
- The substantial performance test (is the job essentially done?) and the holdback release
- Документ
- Estimate of the work left to do
- ERPде
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.