کورس کا تعارف · 3 منٹ

CCDC 2 معاہدے پر ادائیگی وصول کریں (کینیڈا)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

ٹاسک 1 شروع کریں

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.فرضی پراجیکٹ
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
ERP میں کام
5 ٹاسک، تقریباً 2 گھنٹے 5 منٹ

کون کس کو کیا دیتا ہے

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

آپ کے پاس آتا ہے

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionٹاسک 1
    • Directive 7: rock at gridline Fٹاسک 3
    • Work left to complete or correctٹاسک 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedٹاسک 3
آپProject accountant, general contractor

آپ سے جاتا ہے

    • Progress claim 5ٹاسک 1
    • Amount payable now, HST inٹاسک 2
    • Change order 7ٹاسک 3
    • Holdback releaseٹاسک 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesٹاسک 4
    Your subcontractorsPaid after you are paid

پراجیکٹ اور لوگ فرضی ہیں۔ تصاویر تیار کردہ ہیں۔

پراجیکٹ میں آپ کا راستہ

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    ٹاسک 1 · 25 منٹ

    قدروں کے شیڈول سے پیش رفت کا دعویٰ 5

    آپ کا نتیجہ
    Progress claim 5, this month's movement per division
    دستاویز
    Schedule of values with the agreed percent complete
    ERP میں
    Contracts › Progress Claims
  2. Claim

    ٹاسک 2 · 25 منٹ

    ہولڈ بیک، HST اور اصل میں قابل ادائیگی رقم

    آپ کا نتیجہ
    The holdback and the amount payable now, HST included
    دستاویز
    The contract's holdback and HST terms
    ERP میں
    Contracts
  3. Change

    ٹاسک 3 · 25 منٹ

    مارک اپ کے ساتھ تبدیلی کے حکم کی قیمت

    آپ کا نتیجہ
    Change order 7 (a priced change): cost plus two allowances
    دستاویز
    Directive 7, own-forces cost and the sub's quote
    ERP میں
    Variations
  4. Get paid

    ٹاسک 4 · 25 منٹ

    بروقت ادائیگی کا کیلنڈر

    آپ کا نتیجہ
    The payment deadlines and what the disputed division holds back
    دستاویز
    The owner's notice of non-payment
    ERP میں
    Contracts
  5. Get paid

    ٹاسک 5 · 25 منٹ

    خاطر خواہ تکمیل اور ہولڈ بیک کا اجرا

    آپ کا نتیجہ
    The substantial performance test (is the job essentially done?) and the holdback release
    دستاویز
    Estimate of the work left to do
    ERP میں
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
ٹاسک 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
ٹاسک 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
ٹاسک 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
ٹاسک 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

نیلا وہ ہے جو ٹاسک شامل کرتا ہے؛ سرمئی پچھلے مرحلے سے آیا ہے۔

مختصراً. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.