Introduktion til kurset · 3 min
Få betaling på en CCDC 2-kontrakt (Canada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Fiktivt projekt- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Arbejde i ERP
- 5 opgaver, cirka 2 t 5 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
- Firm of architectsConsultant, certifies
- Percent complete per divisionOpgave 1
- Directive 7: rock at gridline FOpgave 3
- Work left to complete or correctOpgave 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedOpgave 3
DigProject accountant, general contractorGår fra dig
- Progress claim 5Opgave 1
- Amount payable now, HST inOpgave 2
- Change order 7Opgave 3
- Holdback releaseOpgave 5
- Their payment, by the Act's datesOpgave 4
Projektet og personerne er fiktive. Portrætterne er genererede.
Din vej gennem sagen
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Opgave 1 · 25 min
Acontofaktura 5 ud fra tilbudslisten
- Du leverer
- Progress claim 5, this month's movement per division
- Dokument
- Schedule of values with the agreed percent complete
- I ERP
- Contracts › Progress Claims
Claim
Opgave 2 · 25 min
Tilbageholdelse, HST og det, der faktisk skal betales
- Du leverer
- The holdback and the amount payable now, HST included
- Dokument
- The contract's holdback and HST terms
- I ERP
- Contracts
Change
Opgave 3 · 25 min
Prissæt et tillægsarbejde med tillæg
- Du leverer
- Change order 7 (a priced change): cost plus two allowances
- Dokument
- Directive 7, own-forces cost and the sub's quote
- I ERP
- Variations
Get paid
Opgave 4 · 25 min
Kalenderen for rettidig betaling
- Du leverer
- The payment deadlines and what the disputed division holds back
- Dokument
- The owner's notice of non-payment
- I ERP
- Contracts
Get paid
Opgave 5 · 25 min
Væsentlig færdiggørelse og frigivelse af tilbageholdelsen
- Du leverer
- The substantial performance test (is the job essentially done?) and the holdback release
- Dokument
- Estimate of the work left to do
- I ERP
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.