Úvod do kurzu · 3 min
Jak dostat zaplaceno u kontraktu CCDC 2 (Kanada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Smyšlený projekt- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Práce v ERP
- Úlohy: 5, asi 2 h 5 min
Kdo komu co předává
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Přichází k vám
- Firm of architectsConsultant, certifies
- Percent complete per divisionÚloha 1
- Directive 7: rock at gridline FÚloha 3
- Work left to complete or correctÚloha 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedÚloha 3
VyProject accountant, general contractorOdchází od vás
- Progress claim 5Úloha 1
- Amount payable now, HST inÚloha 2
- Change order 7Úloha 3
- Holdback releaseÚloha 5
- Their payment, by the Act's datesÚloha 4
Projekt i lidé jsou smyšlení. Portréty jsou vygenerované.
Vaše cesta zakázkou
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Úloha 1 · 25 min
Průběžná žádost o platbu 5 z rozpisu hodnot
- Výstup
- Progress claim 5, this month's movement per division
- Dokument
- Schedule of values with the agreed percent complete
- V ERP
- Contracts › Progress Claims
Claim
Úloha 2 · 25 min
Pozastávka, HST a co se skutečně platí
- Výstup
- The holdback and the amount payable now, HST included
- Dokument
- The contract's holdback and HST terms
- V ERP
- Contracts
Change
Úloha 3 · 25 min
Ocenění změnového listu s přirážkami
- Výstup
- Change order 7 (a priced change): cost plus two allowances
- Dokument
- Directive 7, own-forces cost and the sub's quote
- V ERP
- Variations
Get paid
Úloha 4 · 25 min
Kalendář rychlé platby
- Výstup
- The payment deadlines and what the disputed division holds back
- Dokument
- The owner's notice of non-payment
- V ERP
- Contracts
Get paid
Úloha 5 · 25 min
Podstatné dokončení a uvolnění pozastávky
- Výstup
- The substantial performance test (is the job essentially done?) and the holdback release
- Dokument
- Estimate of the work left to do
- V ERP
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.
Stručně. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.