OpenConstruction Academy
Přihlásit se / Registrace
CS

Úvod do kurzu · 3 min

Jak dostat zaplaceno u kontraktu CCDC 2 (Kanada)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

Začít úlohu 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Smyšlený projekt
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
Práce v ERP
Úlohy: 5, asi 2 h 5 min

Kdo komu co předává

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Přichází k vám

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionÚloha 1
    • Directive 7: rock at gridline FÚloha 3
    • Work left to complete or correctÚloha 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedÚloha 3
VyProject accountant, general contractor

Odchází od vás

    • Progress claim 5Úloha 1
    • Amount payable now, HST inÚloha 2
    • Change order 7Úloha 3
    • Holdback releaseÚloha 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesÚloha 4
    Your subcontractorsPaid after you are paid

Projekt i lidé jsou smyšlení. Portréty jsou vygenerované.

Vaše cesta zakázkou

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Úloha 1 · 25 min

    Průběžná žádost o platbu 5 z rozpisu hodnot

    Výstup
    Progress claim 5, this month's movement per division
    Dokument
    Schedule of values with the agreed percent complete
    V ERP
    Contracts › Progress Claims
  2. Claim

    Úloha 2 · 25 min

    Pozastávka, HST a co se skutečně platí

    Výstup
    The holdback and the amount payable now, HST included
    Dokument
    The contract's holdback and HST terms
    V ERP
    Contracts
  3. Change

    Úloha 3 · 25 min

    Ocenění změnového listu s přirážkami

    Výstup
    Change order 7 (a priced change): cost plus two allowances
    Dokument
    Directive 7, own-forces cost and the sub's quote
    V ERP
    Variations
  4. Get paid

    Úloha 4 · 25 min

    Kalendář rychlé platby

    Výstup
    The payment deadlines and what the disputed division holds back
    Dokument
    The owner's notice of non-payment
    V ERP
    Contracts
  5. Get paid

    Úloha 5 · 25 min

    Podstatné dokončení a uvolnění pozastávky

    Výstup
    The substantial performance test (is the job essentially done?) and the holdback release
    Dokument
    Estimate of the work left to do
    V ERP
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Úloha 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Úloha 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Úloha 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Úloha 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.

Stručně. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.