OpenConstruction Academy
ورود / ثبت‌نام
FA

معرفی دوره · 3 دقیقه

دریافت مطالبات در یک قرارداد CCDC 2 (کانادا)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

شروع تکلیف 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.پروژهٔ خیالی
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
کار در ERP
5 تکلیف، حدود 2 ساعت 5 دقیقه

چه کسی چه چیزی به چه کسی می‌دهد

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

به شما می‌رسد

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionتکلیف 1
    • Directive 7: rock at gridline Fتکلیف 3
    • Work left to complete or correctتکلیف 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedتکلیف 3
شماProject accountant, general contractor

از شما می‌رود

    • Progress claim 5تکلیف 1
    • Amount payable now, HST inتکلیف 2
    • Change order 7تکلیف 3
    • Holdback releaseتکلیف 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesتکلیف 4
    Your subcontractorsPaid after you are paid

پروژه و افراد خیالی‌اند. چهره‌ها ساختگی هستند.

مسیر شما در پروژه

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    تکلیف 1 · 25 دقیقه

    صورت‌وضعیت 5 از جدول مقادیر

    خروجی شما
    Progress claim 5, this month's movement per division
    سند
    Schedule of values with the agreed percent complete
    در ERP
    Contracts › Progress Claims
  2. Claim

    تکلیف 2 · 25 دقیقه

    مبلغ نگهداری، HST و آنچه واقعاً قابل پرداخت است

    خروجی شما
    The holdback and the amount payable now, HST included
    سند
    The contract's holdback and HST terms
    در ERP
    Contracts
  3. Change

    تکلیف 3 · 25 دقیقه

    قیمت‌گذاری دستور تغییر با ضرایب افزوده

    خروجی شما
    Change order 7 (a priced change): cost plus two allowances
    سند
    Directive 7, own-forces cost and the sub's quote
    در ERP
    Variations
  4. Get paid

    تکلیف 4 · 25 دقیقه

    تقویم پرداخت فوری

    خروجی شما
    The payment deadlines and what the disputed division holds back
    سند
    The owner's notice of non-payment
    در ERP
    Contracts
  5. Get paid

    تکلیف 5 · 25 دقیقه

    تکمیل اساسی و آزادسازی مبلغ نگهداری

    خروجی شما
    The substantial performance test (is the job essentially done?) and the holdback release
    سند
    Estimate of the work left to do
    در ERP
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
تکلیف 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
تکلیف 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
تکلیف 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
تکلیف 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

آبی چیزی است که تکلیف اضافه می‌کند؛ خاکستری از مرحلهٔ قبل آمده است.

به‌طور خلاصه. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.