OpenConstruction Academy
Prijava / Registracija
HR

Uvod u tečaj · 3 min

Naplata po ugovoru CCDC 2 (Kanada)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

Započni zadatak 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Izmišljeni projekt
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
Rad u ERP-u
Zadataka: 5, oko 2 h 5 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionZadatak 1
    • Directive 7: rock at gridline FZadatak 3
    • Work left to complete or correctZadatak 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedZadatak 3
ViProject accountant, general contractor

Odlazi od vas

    • Progress claim 5Zadatak 1
    • Amount payable now, HST inZadatak 2
    • Change order 7Zadatak 3
    • Holdback releaseZadatak 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesZadatak 4
    Your subcontractorsPaid after you are paid

Projekt i osobe su izmišljeni. Portreti su generirani.

Vaš put kroz projekt

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Zadatak 1 · 25 min

    Privremena situacija 5 iz plana vrijednosti

    Vaš rezultat
    Progress claim 5, this month's movement per division
    Dokument
    Schedule of values with the agreed percent complete
    U ERP-u
    Contracts › Progress Claims
  2. Claim

    Zadatak 2 · 25 min

    Zadržani iznos, HST i što se zapravo plaća

    Vaš rezultat
    The holdback and the amount payable now, HST included
    Dokument
    The contract's holdback and HST terms
    U ERP-u
    Contracts
  3. Change

    Zadatak 3 · 25 min

    Cijena izmjene s dodacima

    Vaš rezultat
    Change order 7 (a priced change): cost plus two allowances
    Dokument
    Directive 7, own-forces cost and the sub's quote
    U ERP-u
    Variations
  4. Get paid

    Zadatak 4 · 25 min

    Kalendar žurnog plaćanja

    Vaš rezultat
    The payment deadlines and what the disputed division holds back
    Dokument
    The owner's notice of non-payment
    U ERP-u
    Contracts
  5. Get paid

    Zadatak 5 · 25 min

    Bitno dovršenje i otpuštanje zadržanog iznosa

    Vaš rezultat
    The substantial performance test (is the job essentially done?) and the holdback release
    Dokument
    Estimate of the work left to do
    U ERP-u
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Zadatak 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Zadatak 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Zadatak 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Zadatak 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.