Uvod u tečaj · 3 min
Naplata po ugovoru CCDC 2 (Kanada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Izmišljeni projekt- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Rad u ERP-u
- Zadataka: 5, oko 2 h 5 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- Firm of architectsConsultant, certifies
- Percent complete per divisionZadatak 1
- Directive 7: rock at gridline FZadatak 3
- Work left to complete or correctZadatak 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedZadatak 3
ViProject accountant, general contractorOdlazi od vas
- Progress claim 5Zadatak 1
- Amount payable now, HST inZadatak 2
- Change order 7Zadatak 3
- Holdback releaseZadatak 5
- Their payment, by the Act's datesZadatak 4
Projekt i osobe su izmišljeni. Portreti su generirani.
Vaš put kroz projekt
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Zadatak 1 · 25 min
Privremena situacija 5 iz plana vrijednosti
- Vaš rezultat
- Progress claim 5, this month's movement per division
- Dokument
- Schedule of values with the agreed percent complete
- U ERP-u
- Contracts › Progress Claims
Claim
Zadatak 2 · 25 min
Zadržani iznos, HST i što se zapravo plaća
- Vaš rezultat
- The holdback and the amount payable now, HST included
- Dokument
- The contract's holdback and HST terms
- U ERP-u
- Contracts
Change
Zadatak 3 · 25 min
Cijena izmjene s dodacima
- Vaš rezultat
- Change order 7 (a priced change): cost plus two allowances
- Dokument
- Directive 7, own-forces cost and the sub's quote
- U ERP-u
- Variations
Get paid
Zadatak 4 · 25 min
Kalendar žurnog plaćanja
- Vaš rezultat
- The payment deadlines and what the disputed division holds back
- Dokument
- The owner's notice of non-payment
- U ERP-u
- Contracts
Get paid
Zadatak 5 · 25 min
Bitno dovršenje i otpuštanje zadržanog iznosa
- Vaš rezultat
- The substantial performance test (is the job essentially done?) and the holdback release
- Dokument
- Estimate of the work left to do
- U ERP-u
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.