Încasarea plăților pe un contract CCDC 2 (Canada)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

Începe sarcina 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Proiect fictiv
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
Lucru în ERP
5 sarcini, circa 2 h 5 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionSarcina 1
    • Directive 7: rock at gridline FSarcina 3
    • Work left to complete or correctSarcina 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedSarcina 3
TuProject accountant, general contractor

Pleacă de la tine

    • Progress claim 5Sarcina 1
    • Amount payable now, HST inSarcina 2
    • Change order 7Sarcina 3
    • Holdback releaseSarcina 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesSarcina 4
    Your subcontractorsPaid after you are paid

Proiectul și persoanele sunt fictive. Portretele sunt generate.

Traseul tău prin proiect

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Sarcina 1 · 25 min

    Situația de plată 5 pornind de la graficul valorilor

    Produci
    Progress claim 5, this month's movement per division
    Document
    Schedule of values with the agreed percent complete
    În ERP
    Contracts › Progress Claims
  2. Claim

    Sarcina 2 · 25 min

    Reținerea, HST și ce se plătește efectiv

    Produci
    The holdback and the amount payable now, HST included
    Document
    The contract's holdback and HST terms
    În ERP
    Contracts
  3. Change

    Sarcina 3 · 25 min

    Stabilirea prețului unui ordin de modificare cu adaosuri

    Produci
    Change order 7 (a priced change): cost plus two allowances
    Document
    Directive 7, own-forces cost and the sub's quote
    În ERP
    Variations
  4. Get paid

    Sarcina 4 · 25 min

    Calendarul plății prompte

    Produci
    The payment deadlines and what the disputed division holds back
    Document
    The owner's notice of non-payment
    În ERP
    Contracts
  5. Get paid

    Sarcina 5 · 25 min

    Execuția substanțială și eliberarea reținerii

    Produci
    The substantial performance test (is the job essentially done?) and the holdback release
    Document
    Estimate of the work left to do
    În ERP
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Sarcina 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Sarcina 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Sarcina 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Sarcina 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.