Introducere în curs · 3 min
Încasarea plăților pe un contract CCDC 2 (Canada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Proiect fictiv- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Lucru în ERP
- 5 sarcini, circa 2 h 5 min
Cine ce predă cui
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Ajunge la tine
- Firm of architectsConsultant, certifies
- Percent complete per divisionSarcina 1
- Directive 7: rock at gridline FSarcina 3
- Work left to complete or correctSarcina 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedSarcina 3
TuProject accountant, general contractorPleacă de la tine
- Progress claim 5Sarcina 1
- Amount payable now, HST inSarcina 2
- Change order 7Sarcina 3
- Holdback releaseSarcina 5
- Their payment, by the Act's datesSarcina 4
Proiectul și persoanele sunt fictive. Portretele sunt generate.
Traseul tău prin proiect
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Sarcina 1 · 25 min
Situația de plată 5 pornind de la graficul valorilor
- Produci
- Progress claim 5, this month's movement per division
- Document
- Schedule of values with the agreed percent complete
- În ERP
- Contracts › Progress Claims
Claim
Sarcina 2 · 25 min
Reținerea, HST și ce se plătește efectiv
- Produci
- The holdback and the amount payable now, HST included
- Document
- The contract's holdback and HST terms
- În ERP
- Contracts
Change
Sarcina 3 · 25 min
Stabilirea prețului unui ordin de modificare cu adaosuri
- Produci
- Change order 7 (a priced change): cost plus two allowances
- Document
- Directive 7, own-forces cost and the sub's quote
- În ERP
- Variations
Get paid
Sarcina 4 · 25 min
Calendarul plății prompte
- Produci
- The payment deadlines and what the disputed division holds back
- Document
- The owner's notice of non-payment
- În ERP
- Contracts
Get paid
Sarcina 5 · 25 min
Execuția substanțială și eliberarea reținerii
- Produci
- The substantial performance test (is the job essentially done?) and the holdback release
- Document
- Estimate of the work left to do
- În ERP
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.