Få betalt på ett CCDC 2-kontrakt (Kanada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Fiktivt projekt- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Arbete i ERP
- 5 uppgifter, cirka 2 h 5 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- Firm of architectsConsultant, certifies
- Percent complete per divisionUppgift 1
- Directive 7: rock at gridline FUppgift 3
- Work left to complete or correctUppgift 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedUppgift 3
DuProject accountant, general contractorGår från dig
- Progress claim 5Uppgift 1
- Amount payable now, HST inUppgift 2
- Change order 7Uppgift 3
- Holdback releaseUppgift 5
- Their payment, by the Act's datesUppgift 4
Projektet och personerna är fiktiva. Porträtten är genererade.
Din väg genom projektet
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Uppgift 1 · 25 min
Betalningsansökan 5 utifrån värdeschemat
- Du tar fram
- Progress claim 5, this month's movement per division
- Dokument
- Schedule of values with the agreed percent complete
- I ERP
- Contracts › Progress Claims
Claim
Uppgift 2 · 25 min
Innehållning, HST och vad som faktiskt ska betalas
- Du tar fram
- The holdback and the amount payable now, HST included
- Dokument
- The contract's holdback and HST terms
- I ERP
- Contracts
Change
Uppgift 3 · 25 min
Prissätt en ändringsorder med påslag
- Du tar fram
- Change order 7 (a priced change): cost plus two allowances
- Dokument
- Directive 7, own-forces cost and the sub's quote
- I ERP
- Variations
Get paid
Uppgift 4 · 25 min
Kalendern för snabb betalning
- Du tar fram
- The payment deadlines and what the disputed division holds back
- Dokument
- The owner's notice of non-payment
- I ERP
- Contracts
Get paid
Uppgift 5 · 25 min
Väsentligt slutförande och frigörande av innehållningen
- Du tar fram
- The substantial performance test (is the job essentially done?) and the holdback release
- Dokument
- Estimate of the work left to do
- I ERP
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.