Kurssin johdanto · 3 min
Maksun saaminen CCDC 2 -urakkasopimuksessa (Kanada)
You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.
Kuvitteellinen hanke- Building
- Co-operative seniors' residence, four storeys
- Contract
- CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
- Law
- Ontario's Construction Act (payment deadlines and holdback), HST on top
- Työ ERP:ssä
- Tehtäviä 5, noin 2 t 5 min
Kuka antaa mitä kenelle
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tulee sinulle
- Firm of architectsConsultant, certifies
- Percent complete per divisionTehtävä 1
- Directive 7: rock at gridline FTehtävä 3
- Work left to complete or correctTehtävä 5
- Rock-breaking subcontractorSublet part of the change
- Quote, its own markup includedTehtävä 3
SinäProject accountant, general contractorLähtee sinulta
- Progress claim 5Tehtävä 1
- Amount payable now, HST inTehtävä 2
- Change order 7Tehtävä 3
- Holdback releaseTehtävä 5
- Their payment, by the Act's datesTehtävä 4
Hanke ja henkilöt ovat kuvitteellisia. Muotokuvat on luotu tekoälyllä.
Reittisi hankkeen läpi
Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.
Claim
Tehtävä 1 · 25 min
Maksuerälasku 5 arvoluettelon pohjalta
- Tuotat
- Progress claim 5, this month's movement per division
- Asiakirja
- Schedule of values with the agreed percent complete
- ERP:ssä
- Contracts › Progress Claims
Claim
Tehtävä 2 · 25 min
Pidätys, HST ja se, mikä todella maksetaan
- Tuotat
- The holdback and the amount payable now, HST included
- Asiakirja
- The contract's holdback and HST terms
- ERP:ssä
- Contracts
Change
Tehtävä 3 · 25 min
Muutostyön hinnoittelu lisineen
- Tuotat
- Change order 7 (a priced change): cost plus two allowances
- Asiakirja
- Directive 7, own-forces cost and the sub's quote
- ERP:ssä
- Variations
Get paid
Tehtävä 4 · 25 min
Viivytyksettömän maksun kalenteri
- Tuotat
- The payment deadlines and what the disputed division holds back
- Asiakirja
- The owner's notice of non-payment
- ERP:ssä
- Contracts
Get paid
Tehtävä 5 · 25 min
Olennainen täyttäminen ja pidätyksen vapauttaminen
- Tuotat
- The substantial performance test (is the job essentially done?) and the holdback release
- Asiakirja
- Estimate of the work left to do
- ERP:ssä
- Contracts
From a month's work to the cheque
Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.
Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.
Lyhyesti. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.