Maksun saaminen CCDC 2 -urakkasopimuksessa (Kanada)

You are the project accountant at the general contractor on a four-storey seniors' residence in Ontario. Each month the builder claims payment for the share of the work done. In five tasks you take one month from the agreed percent complete to a progress claim and the cheque, price a change order, follow the legal payment deadlines and release the holdback, the share the owner keeps until the end.

Aloita tehtävä 1

A four-storey brick building with its upper floors still in insulation board, a tower crane behind it and two workers in high-visibility vests on a snowy site road.Kuvitteellinen hanke
Tamarack Ridge Seniors' Residence, Phase 2Four-storey co-operative housing · Ontario
Building
Co-operative seniors' residence, four storeys
Contract
CCDC 2 - 2020 Stipulated Price, the standard Canadian fixed-price contract
Law
Ontario's Construction Act (payment deadlines and holdback), HST on top
Työ ERP:ssä
Tehtäviä 5, noin 2 t 5 min

Kuka antaa mitä kenelle

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tulee sinulle

  • Firm of architectsConsultant, certifies
    • Percent complete per divisionTehtävä 1
    • Directive 7: rock at gridline FTehtävä 3
    • Work left to complete or correctTehtävä 5
  • Rock-breaking subcontractorSublet part of the change
    • Quote, its own markup includedTehtävä 3
SinäProject accountant, general contractor

Lähtee sinulta

    • Progress claim 5Tehtävä 1
    • Amount payable now, HST inTehtävä 2
    • Change order 7Tehtävä 3
    • Holdback releaseTehtävä 5
    Housing co-operativeOwner, pays the claims
    • Their payment, by the Act's datesTehtävä 4
    Your subcontractorsPaid after you are paid

Hanke ja henkilöt ovat kuvitteellisia. Muotokuvat on luotu tekoälyllä.

Reittisi hankkeen läpi

Two tasks build the claim and what it pays, one prices a change, two follow the money through the Act's deadlines to the end of the job. Start with task 1: in Contracts you enter this month's percent complete for each division.

  1. Claim

    Tehtävä 1 · 25 min

    Maksuerälasku 5 arvoluettelon pohjalta

    Tuotat
    Progress claim 5, this month's movement per division
    Asiakirja
    Schedule of values with the agreed percent complete
    ERP:ssä
    Contracts › Progress Claims
  2. Claim

    Tehtävä 2 · 25 min

    Pidätys, HST ja se, mikä todella maksetaan

    Tuotat
    The holdback and the amount payable now, HST included
    Asiakirja
    The contract's holdback and HST terms
    ERP:ssä
    Contracts
  3. Change

    Tehtävä 3 · 25 min

    Muutostyön hinnoittelu lisineen

    Tuotat
    Change order 7 (a priced change): cost plus two allowances
    Asiakirja
    Directive 7, own-forces cost and the sub's quote
    ERP:ssä
    Variations
  4. Get paid

    Tehtävä 4 · 25 min

    Viivytyksettömän maksun kalenteri

    Tuotat
    The payment deadlines and what the disputed division holds back
    Asiakirja
    The owner's notice of non-payment
    ERP:ssä
    Contracts
  5. Get paid

    Tehtävä 5 · 25 min

    Olennainen täyttäminen ja pidätyksen vapauttaminen

    Tuotat
    The substantial performance test (is the job essentially done?) and the holdback release
    Asiakirja
    Estimate of the work left to do
    ERP:ssä
    Contracts

From a month's work to the cheque

Each bar is the money of one claim at one step. Task 3 prices a change on its own; it joins the contract price that task 5 tests.

This month's work
Tehtävä 1MovementPercent complete times each division's value, less what was certified before. Only the month goes on the claim.
HST on the netHoldback, keptNet, invoiced now
Tehtävä 2Holdback and HSTThe owner keeps the statutory holdback on the value of the work. HST is charged on the net amount invoiced now.
Holdback, keptDisputed, waitsUndisputed, paid on time
Tehtävä 4DisputeA notice of non-payment given in time holds back only the disputed division. The rest is due by the Act's deadline, moved past holidays.
HST on the holdbackHoldback releasedPaid on the claims
Tehtävä 5ReleaseOnce the work is substantially performed and the lien period, when unpaid trades can claim, has run, the holdback is paid, with its HST invoiced then.

Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.

Lyhyesti. Claim only the month, hold back on the value of the work, charge HST on what is invoiced, and pay to the Act's calendar.