Measure the gross internal floor area and say what is in it and what is not.
Move a benchmark rate to your base date and then to your location.
Multiply the two into an order of cost estimate, and say what it leaves out.
1 / 4
What the client needs first
At concept stage there are sketches, not elements. The client still needs a number to decide whether the project can go ahead. NRM 1 gives it as an order of cost estimate: a floor area times a cost per m² taken from similar buildings. It is coarse on purpose, and it becomes the yardstick every later cost plan is checked against.
Eksempel. In this course the estimate covers building works only, elements 1 to 8. VAT, design fees and facilitating works stay out, and the client holds them in a separate budget.
2 / 4
GIFA: the area costs are measured on
The gross internal floor area is measured to the inside face of the external walls, on every floor. It is the measure benchmark rates are published on, so your area must be measured the same way or the rate does not fit it.
Eksempel. The net internal area leaves out circulation, toilets and plant. It is smaller than GIFA and answers a different question: how much space can be let or used.
Internal walls, columns, partitionsIn
Stairs and lift shafts, on every floorIn
Enclosed plant room on the roofIn
Atrium or other voidLowest level only
Open canopy, external escape stairOut
Net internal area: a different measureNot used
3 / 4
Measure inside the walls
Drawings give external dimensions. Take the wall thickness off both ends of each dimension to reach the inside faces. Then add the floors, counting a void once, at the level where it has a floor under it.
Eksempel. A floor drawn 30.0 m × 16.0 m with walls 0.30 m thick measures 29.40 × 15.40 m inside. That is 452.76 m², not 480.00 m²: the walls alone would add 27.24 m² to every floor.
Floor inside the external walls
Atrium void: counted on the lowest floor only
4 / 4
Move the rate in time, then in place
A benchmark rate is stated at a date and for an average location. Bring it to your base date with a tender price index: later index divided by earlier index. Then multiply by the location factor for your site. A factor below 1.00 means building there costs less than the average.
Eksempel. The estimate stops at the base date. The rise from there to the tender date is added once, later, as an inflation allowance. Put it in the rate now and it will be counted twice.
Benchmark, per m² GIFAAt its own date
× time factorNew index ÷ old
× location factorSite ÷ average
= rate for the estimateAt the base date
A two-storey clinic, from drawing to estimate
A smaller building with different numbers from your task. Type your guess before you open each step.
Ikke i målestokk
Oppgaven
Two floors, each 36.0 m × 18.0 m outside, external walls 0.35 m thick.
A void 6.0 m × 4.0 m inside rises through the first floor. An open canopy at the entrance.
Benchmark £2,900.00 per m² GIFA. Index 300 at the benchmark date, 312 at your base date. Location factor 1.02.
One floor, external dimensions shown; you price the area inside the walls
One floor, external dimensions shown; you price the area inside the walls
Trinn 1 av 4
One floor, inside the walls
Take the walls off both ends of each dimension. What is the internal area of one floor?
Hint: Two wall thicknesses come off each dimension, one at each end.
36.0 m − 2 × 0.35 m = 35.3 m. 18.0 m − 2 × 0.35 m = 17.3 m. One floor: 35.3 m × 17.3 m = 610.69 m².
First floor
Void, no floor at this level
First floor
Void, no floor at this level
Trinn 2 av 4
GIFA
Two floors, less the void where it has no floor. The canopy is open. What is the GIFA?
Hint: The void has a floor on the ground floor, so only the first floor loses it.
610.69 m² × 2, less the void 6.0 m × 4.0 m = 24.00 m² on the first floor: 1,197.38 m². The canopy is not enclosed, so it is not GIFA.
Benchmark£2,900.00
At the base date?
At the base date, this location?
Benchmark£2,900.00
At the base date£3,016.00
At the base date, this location£3,076.32
Trinn 3 av 4
The rate at your date and place
Time factor to four decimals, then the location factor. Round to the penny after each step. What rate do you use?
Hint: Later index over earlier index. Prices rose, so the factor is above 1.
312 ÷ 300 = 1.04. £2,900.00 × 1.04 = £3,016.00 at the base date. × 1.02 for the location = £3,076.32.
GIFA1,197.38 m²
Rate per m² GIFA£3,076.32
Order of cost estimate?
GIFA1,197.38 m²
Rate per m² GIFA£3,076.32
Order of cost estimate£3,683,524.04
Trinn 4 av 4
The order of cost estimate
GIFA times the adjusted rate. Give pence.
Hint: Use the GIFA from step 2 and the rate from step 3.
1,197.38 m² × £3,076.32 = £3,683,524.04. Building works only, at the base date: no VAT, no fees, no inflation to the tender date.
Kort sagt. Measure inside the walls, count a void once, move the rate in time and then in place, and multiply. In the task the bill line holds the GIFA as its quantity and the adjusted rate as its unit rate.
Test deg selv
Spørsmål 1 av 3
Which of these is part of GIFA?
It is enclosed and inside the building envelope, so it counts.
It is not enclosed. Report it separately, not in GIFA.
External stairs are outside the building and are not GIFA.
A void has no floor above its lowest level. Count it once, at the bottom.
Spørsmål 2 av 3
A benchmark is £2,500.00 per m² GIFA at index 280. Your base date has index 294. The location factor is 0.95. What rate do you use? Round to the penny after each step.