OpenConstruction Academy
Logg inn / Registrer deg
NO

Introduksjon til kurset · 3 min

Elementbasert kostnadsplanlegging på konseptstadiet (UK, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

Start oppgave 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Fiktivt prosjekt
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
Arbeid i ERP
5 oppgaver, omtrent 3 t 20 min

Hvem gir hva til hvem

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Kommer til deg

  • ArchitectLeads the design team
    • Concept drawingsOppgave 1
    • Option B: steel frame, rendered wallsOppgave 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inOppgave 5
DuCost consultant, working for the client

Går fra deg

    • Order of cost estimateOppgave 1
    • Cost plan 1 and the cost limitOppgave 3
    • Saving from option BOppgave 4
    • Cost plan 2 against the budgetOppgave 5
    The health trustClient, sets the budget

Prosjektet og personene er fiktive. Portrettene er genererte.

Din vei gjennom prosjektet

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Oppgave 1 · 40 min

    GIFA og rammekostnadsoverslaget

    Du leverer
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Dokument
    Concept drawings, a benchmark rate and price indices
    I ERP
    Bill of Quantities
  2. Cost plan 1

    Oppgave 2 · 50 min

    Kostnadsplan per bygningsdel

    Du leverer
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Dokument
    Element unit quantities and rates
    I ERP
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Oppgave 3 · 40 min

    Fra bygningsarbeider til kostnadsramme

    Du leverer
    The cost limit at the tender date
    Dokument
    Allowances and the inflation forecast
    I ERP
    Bill of Quantities, Markups
  4. Cost plan 2

    Oppgave 4 · 40 min

    Verdioptimalisering: stålkonstruksjon og pussede vegger

    Du leverer
    The saving from option B, after the redesign fee
    Dokument
    Option B rates from the design team
    I ERP
    Bill of Quantities
  5. Cost plan 2

    Oppgave 5 · 30 min

    Avstem kostnadsplan 2 mot budsjettet

    Du leverer
    The variance to budget and the cost per m²
    Dokument
    The Trust's budget letter
    I ERP
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Oppgave 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Oppgave 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Oppgave 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Oppgave 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Oppgave 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Blått er det oppgaven legger til; grått er overført fra før.

Kort sagt. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.