Panimula ng kurso · 3 min

Elemental cost planning sa concept stage (UK, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

Simulan ang gawain 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Kathang-isip na proyekto
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
Trabaho sa ERP
5 gawain, mga 3 oras 20 min

Sino ang nagbibigay ng ano kanino

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Dumarating sa iyo

  • ArchitectLeads the design team
    • Concept drawingsGawain 1
    • Option B: steel frame, rendered wallsGawain 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inGawain 5
IkawCost consultant, working for the client

Lumalabas sa iyo

    • Order of cost estimateGawain 1
    • Cost plan 1 and the cost limitGawain 3
    • Saving from option BGawain 4
    • Cost plan 2 against the budgetGawain 5
    The health trustClient, sets the budget

Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.

Ang ruta mo sa proyekto

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Gawain 1 · 40 min

    Ang GIFA at ang order-of-cost estimate

    Ang gagawin mo
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Dokumento
    Concept drawings, a benchmark rate and price indices
    Sa ERP
    Bill of Quantities
  2. Cost plan 1

    Gawain 2 · 50 min

    Ang elemental cost plan

    Ang gagawin mo
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Dokumento
    Element unit quantities and rates
    Sa ERP
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Gawain 3 · 40 min

    Mula sa building works hanggang sa cost limit

    Ang gagawin mo
    The cost limit at the tender date
    Dokumento
    Allowances and the inflation forecast
    Sa ERP
    Bill of Quantities, Markups
  4. Cost plan 2

    Gawain 4 · 40 min

    Value engineering: steel frame at rendered na mga pader

    Ang gagawin mo
    The saving from option B, after the redesign fee
    Dokumento
    Option B rates from the design team
    Sa ERP
    Bill of Quantities
  5. Cost plan 2

    Gawain 5 · 30 min

    Pagtugmain ang cost plan 2 sa badyet

    Ang gagawin mo
    The variance to budget and the cost per m²
    Dokumento
    The Trust's budget letter
    Sa ERP
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Gawain 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Gawain 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Gawain 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Gawain 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Gawain 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.