معرفی دوره · 3 دقیقه
برنامهریزی هزینه عنصری در مرحله مفهومی (بریتانیا، RICS NRM 1)
You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.
پروژهٔ خیالی- Building
- Three storeys, atrium and an enclosed roof plant room
- Rules
- RICS NRM 1, the UK rules for early cost estimates and cost plans
- Story
- Concept design, November 2026 to January 2027
- کار در ERP
- 5 تکلیف، حدود 3 ساعت 20 دقیقه
چه کسی چه چیزی به چه کسی میدهد
Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.
به شما میرسد
ArchitectLeads the design team- Concept drawingsتکلیف 1
- Option B: steel frame, rendered wallsتکلیف 4
- Budget letterFrom the Trust's board
- Total project budget, VAT inتکلیف 5
شماCost consultant, working for the clientاز شما میرود
- Order of cost estimateتکلیف 1
- Cost plan 1 and the cost limitتکلیف 3
- Saving from option Bتکلیف 4
- Cost plan 2 against the budgetتکلیف 5
The health trustClient, sets the budget
پروژه و افراد خیالیاند. چهرهها ساختگی هستند.
مسیر شما در پروژه
One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.
Order of cost
تکلیف 1 · 40 دقیقه
GIFA و برآورد مرتبه هزینه
- خروجی شما
- Floor area (GIFA, measured inside the outer walls) and the first estimate
- سند
- Concept drawings, a benchmark rate and price indices
- در ERP
- Bill of Quantities
Cost plan 1
تکلیف 2 · 50 دقیقه
طرح هزینه عنصری
- خروجی شما
- Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
- سند
- Element unit quantities and rates
- در ERP
- Bill of Quantities, Cost Breakdown
Cost plan 1
تکلیف 3 · 40 دقیقه
از کارهای ساختمانی تا حد هزینه
- خروجی شما
- The cost limit at the tender date
- سند
- Allowances and the inflation forecast
- در ERP
- Bill of Quantities, Markups
Cost plan 2
تکلیف 4 · 40 دقیقه
مهندسی ارزش: اسکلت فولادی و دیوارهای رندشده
- خروجی شما
- The saving from option B, after the redesign fee
- سند
- Option B rates from the design team
- در ERP
- Bill of Quantities
Cost plan 2
تکلیف 5 · 30 دقیقه
تطبیق طرح هزینه 2 با بودجه
- خروجی شما
- The variance to budget and the cost per m²
- سند
- The Trust's budget letter
- در ERP
- Bill of Quantities, Cost Breakdown
How a floor area becomes a cost limit
Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.
آبی چیزی است که تکلیف اضافه میکند؛ خاکستری از مرحلهٔ قبل آمده است.
بهطور خلاصه. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.