You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

شروع تکلیف 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.پروژهٔ خیالی
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
کار در ERP
5 تکلیف، حدود 3 ساعت 20 دقیقه

چه کسی چه چیزی به چه کسی می‌دهد

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

به شما می‌رسد

  • ArchitectLeads the design team
    • Concept drawingsتکلیف 1
    • Option B: steel frame, rendered wallsتکلیف 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inتکلیف 5
شماCost consultant, working for the client

از شما می‌رود

    • Order of cost estimateتکلیف 1
    • Cost plan 1 and the cost limitتکلیف 3
    • Saving from option Bتکلیف 4
    • Cost plan 2 against the budgetتکلیف 5
    The health trustClient, sets the budget

پروژه و افراد خیالی‌اند. چهره‌ها ساختگی هستند.

مسیر شما در پروژه

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    تکلیف 1 · 40 دقیقه

    GIFA و برآورد مرتبه هزینه

    خروجی شما
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    سند
    Concept drawings, a benchmark rate and price indices
    در ERP
    Bill of Quantities
  2. Cost plan 1

    تکلیف 2 · 50 دقیقه

    طرح هزینه عنصری

    خروجی شما
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    سند
    Element unit quantities and rates
    در ERP
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    تکلیف 3 · 40 دقیقه

    از کارهای ساختمانی تا حد هزینه

    خروجی شما
    The cost limit at the tender date
    سند
    Allowances and the inflation forecast
    در ERP
    Bill of Quantities, Markups
  4. Cost plan 2

    تکلیف 4 · 40 دقیقه

    مهندسی ارزش: اسکلت فولادی و دیوارهای رندشده

    خروجی شما
    The saving from option B, after the redesign fee
    سند
    Option B rates from the design team
    در ERP
    Bill of Quantities
  5. Cost plan 2

    تکلیف 5 · 30 دقیقه

    تطبیق طرح هزینه 2 با بودجه

    خروجی شما
    The variance to budget and the cost per m²
    سند
    The Trust's budget letter
    در ERP
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
تکلیف 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
تکلیف 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
تکلیف 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
تکلیف 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
تکلیف 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

آبی چیزی است که تکلیف اضافه می‌کند؛ خاکستری از مرحلهٔ قبل آمده است.

به‌طور خلاصه. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.