Kurssin johdanto · 3 min

Elementtipohjainen kustannussuunnittelu luonnosvaiheessa (UK, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

Aloita tehtävä 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Kuvitteellinen hanke
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
Työ ERP:ssä
Tehtäviä 5, noin 3 t 20 min

Kuka antaa mitä kenelle

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Tulee sinulle

  • ArchitectLeads the design team
    • Concept drawingsTehtävä 1
    • Option B: steel frame, rendered wallsTehtävä 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inTehtävä 5
SinäCost consultant, working for the client

Lähtee sinulta

    • Order of cost estimateTehtävä 1
    • Cost plan 1 and the cost limitTehtävä 3
    • Saving from option BTehtävä 4
    • Cost plan 2 against the budgetTehtävä 5
    The health trustClient, sets the budget

Hanke ja henkilöt ovat kuvitteellisia. Muotokuvat on luotu tekoälyllä.

Reittisi hankkeen läpi

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Tehtävä 1 · 40 min

    GIFA ja kustannusarvio (order-of-cost estimate)

    Tuotat
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Asiakirja
    Concept drawings, a benchmark rate and price indices
    ERP:ssä
    Bill of Quantities
  2. Cost plan 1

    Tehtävä 2 · 50 min

    Rakennusosittainen kustannussuunnitelma

    Tuotat
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Asiakirja
    Element unit quantities and rates
    ERP:ssä
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Tehtävä 3 · 40 min

    Rakennustöistä kustannusrajaan

    Tuotat
    The cost limit at the tender date
    Asiakirja
    Allowances and the inflation forecast
    ERP:ssä
    Bill of Quantities, Markups
  4. Cost plan 2

    Tehtävä 4 · 40 min

    Arvosuunnittelu: teräsrunko ja rappausseinät

    Tuotat
    The saving from option B, after the redesign fee
    Asiakirja
    Option B rates from the design team
    ERP:ssä
    Bill of Quantities
  5. Cost plan 2

    Tehtävä 5 · 30 min

    Sovita kustannussuunnitelma 2 budjettiin

    Tuotat
    The variance to budget and the cost per m²
    Asiakirja
    The Trust's budget letter
    ERP:ssä
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Tehtävä 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Tehtävä 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Tehtävä 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Tehtävä 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Tehtävä 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.

Lyhyesti. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.