Kurssin johdanto · 3 min
Elementtipohjainen kustannussuunnittelu luonnosvaiheessa (UK, RICS NRM 1)
You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.
Kuvitteellinen hanke- Building
- Three storeys, atrium and an enclosed roof plant room
- Rules
- RICS NRM 1, the UK rules for early cost estimates and cost plans
- Story
- Concept design, November 2026 to January 2027
- Työ ERP:ssä
- Tehtäviä 5, noin 3 t 20 min
Kuka antaa mitä kenelle
Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.
Tulee sinulle
ArchitectLeads the design team- Concept drawingsTehtävä 1
- Option B: steel frame, rendered wallsTehtävä 4
- Budget letterFrom the Trust's board
- Total project budget, VAT inTehtävä 5
SinäCost consultant, working for the clientLähtee sinulta
- Order of cost estimateTehtävä 1
- Cost plan 1 and the cost limitTehtävä 3
- Saving from option BTehtävä 4
- Cost plan 2 against the budgetTehtävä 5
The health trustClient, sets the budget
Hanke ja henkilöt ovat kuvitteellisia. Muotokuvat on luotu tekoälyllä.
Reittisi hankkeen läpi
One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.
Order of cost
Tehtävä 1 · 40 min
GIFA ja kustannusarvio (order-of-cost estimate)
- Tuotat
- Floor area (GIFA, measured inside the outer walls) and the first estimate
- Asiakirja
- Concept drawings, a benchmark rate and price indices
- ERP:ssä
- Bill of Quantities
Cost plan 1
Tehtävä 2 · 50 min
Rakennusosittainen kustannussuunnitelma
- Tuotat
- Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
- Asiakirja
- Element unit quantities and rates
- ERP:ssä
- Bill of Quantities, Cost Breakdown
Cost plan 1
Tehtävä 3 · 40 min
Rakennustöistä kustannusrajaan
- Tuotat
- The cost limit at the tender date
- Asiakirja
- Allowances and the inflation forecast
- ERP:ssä
- Bill of Quantities, Markups
Cost plan 2
Tehtävä 4 · 40 min
Arvosuunnittelu: teräsrunko ja rappausseinät
- Tuotat
- The saving from option B, after the redesign fee
- Asiakirja
- Option B rates from the design team
- ERP:ssä
- Bill of Quantities
Cost plan 2
Tehtävä 5 · 30 min
Sovita kustannussuunnitelma 2 budjettiin
- Tuotat
- The variance to budget and the cost per m²
- Asiakirja
- The Trust's budget letter
- ERP:ssä
- Bill of Quantities, Cost Breakdown
How a floor area becomes a cost limit
Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.
Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.
Lyhyesti. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.