Introducere în curs · 3 min
Planificarea costurilor pe elemente în faza de concept (Regatul Unit, RICS NRM 1)
You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.
Proiect fictiv- Building
- Three storeys, atrium and an enclosed roof plant room
- Rules
- RICS NRM 1, the UK rules for early cost estimates and cost plans
- Story
- Concept design, November 2026 to January 2027
- Lucru în ERP
- 5 sarcini, circa 3 h 20 min
Cine ce predă cui
Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.
Ajunge la tine
ArchitectLeads the design team- Concept drawingsSarcina 1
- Option B: steel frame, rendered wallsSarcina 4
- Budget letterFrom the Trust's board
- Total project budget, VAT inSarcina 5
TuCost consultant, working for the clientPleacă de la tine
- Order of cost estimateSarcina 1
- Cost plan 1 and the cost limitSarcina 3
- Saving from option BSarcina 4
- Cost plan 2 against the budgetSarcina 5
The health trustClient, sets the budget
Proiectul și persoanele sunt fictive. Portretele sunt generate.
Traseul tău prin proiect
One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.
Order of cost
Sarcina 1 · 40 min
GIFA și estimarea orientativă a costului
- Produci
- Floor area (GIFA, measured inside the outer walls) and the first estimate
- Document
- Concept drawings, a benchmark rate and price indices
- În ERP
- Bill of Quantities
Cost plan 1
Sarcina 2 · 50 min
Planul de costuri pe elemente
- Produci
- Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
- Document
- Element unit quantities and rates
- În ERP
- Bill of Quantities, Cost Breakdown
Cost plan 1
Sarcina 3 · 40 min
De la lucrările de construcție la limita de cost
- Produci
- The cost limit at the tender date
- Document
- Allowances and the inflation forecast
- În ERP
- Bill of Quantities, Markups
Cost plan 2
Sarcina 4 · 40 min
Inginerie valorică: structură metalică și pereți tencuiți
- Produci
- The saving from option B, after the redesign fee
- Document
- Option B rates from the design team
- În ERP
- Bill of Quantities
Cost plan 2
Sarcina 5 · 30 min
Reconcilierea planului de costuri 2 cu bugetul
- Produci
- The variance to budget and the cost per m²
- Document
- The Trust's budget letter
- În ERP
- Bill of Quantities, Cost Breakdown
How a floor area becomes a cost limit
Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.