Introducere în curs · 3 min

Planificarea costurilor pe elemente în faza de concept (Regatul Unit, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

Începe sarcina 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Proiect fictiv
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
Lucru în ERP
5 sarcini, circa 3 h 20 min

Cine ce predă cui

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Ajunge la tine

  • ArchitectLeads the design team
    • Concept drawingsSarcina 1
    • Option B: steel frame, rendered wallsSarcina 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inSarcina 5
TuCost consultant, working for the client

Pleacă de la tine

    • Order of cost estimateSarcina 1
    • Cost plan 1 and the cost limitSarcina 3
    • Saving from option BSarcina 4
    • Cost plan 2 against the budgetSarcina 5
    The health trustClient, sets the budget

Proiectul și persoanele sunt fictive. Portretele sunt generate.

Traseul tău prin proiect

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Sarcina 1 · 40 min

    GIFA și estimarea orientativă a costului

    Produci
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Document
    Concept drawings, a benchmark rate and price indices
    În ERP
    Bill of Quantities
  2. Cost plan 1

    Sarcina 2 · 50 min

    Planul de costuri pe elemente

    Produci
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Document
    Element unit quantities and rates
    În ERP
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Sarcina 3 · 40 min

    De la lucrările de construcție la limita de cost

    Produci
    The cost limit at the tender date
    Document
    Allowances and the inflation forecast
    În ERP
    Bill of Quantities, Markups
  4. Cost plan 2

    Sarcina 4 · 40 min

    Inginerie valorică: structură metalică și pereți tencuiți

    Produci
    The saving from option B, after the redesign fee
    Document
    Option B rates from the design team
    În ERP
    Bill of Quantities
  5. Cost plan 2

    Sarcina 5 · 30 min

    Reconcilierea planului de costuri 2 cu bugetul

    Produci
    The variance to budget and the cost per m²
    Document
    The Trust's budget letter
    În ERP
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Sarcina 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Sarcina 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Sarcina 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Sarcina 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Sarcina 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.