Концепция стадиясындагы элементтик чыгым планы (Улуу Британия, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

1-тапшырманы баштоо

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Ойдон чыгарылган долбоор
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
ERPдеги иш
Тапшырмалар: 5, болжол менен 3 саат 20 мүн

Ким кимге эмне берет

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Сизге келет

  • ArchitectLeads the design team
    • Concept drawings1-тапшырма
    • Option B: steel frame, rendered walls4-тапшырма
  • Budget letterFrom the Trust's board
    • Total project budget, VAT in5-тапшырма
СизCost consultant, working for the client

Сизден кетет

    • Order of cost estimate1-тапшырма
    • Cost plan 1 and the cost limit3-тапшырма
    • Saving from option B4-тапшырма
    • Cost plan 2 against the budget5-тапшырма
    The health trustClient, sets the budget

Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.

Долбоор боюнча жолуңуз

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    1-тапшырма · 40 мүн

    GIFA жана чыгымдын тартиптик эсеби

    Натыйжа
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Документ
    Concept drawings, a benchmark rate and price indices
    ERPде
    Bill of Quantities
  2. Cost plan 1

    2-тапшырма · 50 мүн

    Элементтик чыгым планы

    Натыйжа
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Документ
    Element unit quantities and rates
    ERPде
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    3-тапшырма · 40 мүн

    Курулуш иштеринен чыгым чегине чейин

    Натыйжа
    The cost limit at the tender date
    Документ
    Allowances and the inflation forecast
    ERPде
    Bill of Quantities, Markups
  4. Cost plan 2

    4-тапшырма · 40 мүн

    Баалуулук инженериясы: болот каркас жана сыдырылган дубалдар

    Натыйжа
    The saving from option B, after the redesign fee
    Документ
    Option B rates from the design team
    ERPде
    Bill of Quantities
  5. Cost plan 2

    5-тапшырма · 30 мүн

    2-чыгым планын бюджет менен салыштырып тууралоо

    Натыйжа
    The variance to budget and the cost per m²
    Документ
    The Trust's budget letter
    ERPде
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
1-тапшырмаOrder of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
2-тапшырмаElemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
3-тапшырмаCost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
4-тапшырмаOption BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
5-тапшырмаAgainst the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.