Курска киришүү · 3 мүн
Концепция стадиясындагы элементтик чыгым планы (Улуу Британия, RICS NRM 1)
You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.
Ойдон чыгарылган долбоор- Building
- Three storeys, atrium and an enclosed roof plant room
- Rules
- RICS NRM 1, the UK rules for early cost estimates and cost plans
- Story
- Concept design, November 2026 to January 2027
- ERPдеги иш
- Тапшырмалар: 5, болжол менен 3 саат 20 мүн
Ким кимге эмне берет
Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.
Сизге келет
ArchitectLeads the design team- Concept drawings1-тапшырма
- Option B: steel frame, rendered walls4-тапшырма
- Budget letterFrom the Trust's board
- Total project budget, VAT in5-тапшырма
СизCost consultant, working for the clientСизден кетет
- Order of cost estimate1-тапшырма
- Cost plan 1 and the cost limit3-тапшырма
- Saving from option B4-тапшырма
- Cost plan 2 against the budget5-тапшырма
The health trustClient, sets the budget
Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.
Долбоор боюнча жолуңуз
One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.
Order of cost
1-тапшырма · 40 мүн
GIFA жана чыгымдын тартиптик эсеби
- Натыйжа
- Floor area (GIFA, measured inside the outer walls) and the first estimate
- Документ
- Concept drawings, a benchmark rate and price indices
- ERPде
- Bill of Quantities
Cost plan 1
2-тапшырма · 50 мүн
Элементтик чыгым планы
- Натыйжа
- Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
- Документ
- Element unit quantities and rates
- ERPде
- Bill of Quantities, Cost Breakdown
Cost plan 1
3-тапшырма · 40 мүн
Курулуш иштеринен чыгым чегине чейин
- Натыйжа
- The cost limit at the tender date
- Документ
- Allowances and the inflation forecast
- ERPде
- Bill of Quantities, Markups
Cost plan 2
4-тапшырма · 40 мүн
Баалуулук инженериясы: болот каркас жана сыдырылган дубалдар
- Натыйжа
- The saving from option B, after the redesign fee
- Документ
- Option B rates from the design team
- ERPде
- Bill of Quantities
Cost plan 2
5-тапшырма · 30 мүн
2-чыгым планын бюджет менен салыштырып тууралоо
- Натыйжа
- The variance to budget and the cost per m²
- Документ
- The Trust's budget letter
- ERPде
- Bill of Quantities, Cost Breakdown
How a floor area becomes a cost limit
Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.