OpenConstruction Academy
Нэвтрэх / Бүртгүүлэх
MN

Сургалтын танилцуулга · 3 мин

Концепцийн шатны элементийн зардлын төлөвлөгөө (Их Британи, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

1-р даалгаврыг эхлэх

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Зохиомол төсөл
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 3 цаг 20 мин

Хэн хэнд юу дамжуулдаг

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Танд ирдэг

  • ArchitectLeads the design team
    • Concept drawingsДаалгавар 1
    • Option B: steel frame, rendered wallsДаалгавар 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inДаалгавар 5
ТаCost consultant, working for the client

Танаас гардаг

    • Order of cost estimateДаалгавар 1
    • Cost plan 1 and the cost limitДаалгавар 3
    • Saving from option BДаалгавар 4
    • Cost plan 2 against the budgetДаалгавар 5
    The health trustClient, sets the budget

Төсөл ба хүмүүс зохиомол. Хөрөг зургууд үүсгэгдсэн.

Төслөөр явах таны зам

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Даалгавар 1 · 40 мин

    GIFA ба зардлын эрэмбийн тооцоо

    Үр дүн
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Баримт бичиг
    Concept drawings, a benchmark rate and price indices
    ERP дээр
    Bill of Quantities
  2. Cost plan 1

    Даалгавар 2 · 50 мин

    Элементийн зардлын төлөвлөгөө

    Үр дүн
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Баримт бичиг
    Element unit quantities and rates
    ERP дээр
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Даалгавар 3 · 40 мин

    Барилгын ажлаас зардлын хязгаар хүртэл

    Үр дүн
    The cost limit at the tender date
    Баримт бичиг
    Allowances and the inflation forecast
    ERP дээр
    Bill of Quantities, Markups
  4. Cost plan 2

    Даалгавар 4 · 40 мин

    Үнэ цэнийн инженерчлэл: ган каркас ба шохойн ханын өнгөлгөө

    Үр дүн
    The saving from option B, after the redesign fee
    Баримт бичиг
    Option B rates from the design team
    ERP дээр
    Bill of Quantities
  5. Cost plan 2

    Даалгавар 5 · 30 мин

    Зардлын төлөвлөгөө 2-ыг төсөвтэй тулгах

    Үр дүн
    The variance to budget and the cost per m²
    Баримт бичиг
    The Trust's budget letter
    ERP дээр
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Даалгавар 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Даалгавар 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Даалгавар 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Даалгавар 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Даалгавар 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.