OpenConstruction Academy
Sign in / Register
EN

Course introduction · 3 min

Elemental cost planning at concept stage (UK, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

Start task 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Fictional project
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
Work in the ERP
5 tasks, about 3 h 20 min

Who hands what to whom

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Comes to you

  • ArchitectLeads the design team
    • Concept drawingsTask 1
    • Option B: steel frame, rendered wallsTask 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inTask 5
YouCost consultant, working for the client

Goes from you

    • Order of cost estimateTask 1
    • Cost plan 1 and the cost limitTask 3
    • Saving from option BTask 4
    • Cost plan 2 against the budgetTask 5
    The health trustClient, sets the budget

The project and the people are fictional. Portraits are generated.

Your route through the job

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Task 1 · 40 min

    GIFA and the order-of-cost estimate

    You produce
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Document
    Concept drawings, a benchmark rate and price indices
    In the ERP
    Bill of Quantities
  2. Cost plan 1

    Task 2 · 50 min

    The elemental cost plan

    You produce
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Document
    Element unit quantities and rates
    In the ERP
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Task 3 · 40 min

    From building works to the cost limit

    You produce
    The cost limit at the tender date
    Document
    Allowances and the inflation forecast
    In the ERP
    Bill of Quantities, Markups
  4. Cost plan 2

    Task 4 · 40 min

    Value engineering: steel frame and rendered walls

    You produce
    The saving from option B, after the redesign fee
    Document
    Option B rates from the design team
    In the ERP
    Bill of Quantities
  5. Cost plan 2

    Task 5 · 30 min

    Reconcile cost plan 2 to the budget

    You produce
    The variance to budget and the cost per m²
    Document
    The Trust's budget letter
    In the ERP
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Task 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Task 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Task 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Task 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Task 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Blue is what the task adds; grey is carried over from before.

In short. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.