Course introduction · 3 min
Elemental cost planning at concept stage (UK, RICS NRM 1)
You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.
Fictional project- Building
- Three storeys, atrium and an enclosed roof plant room
- Rules
- RICS NRM 1, the UK rules for early cost estimates and cost plans
- Story
- Concept design, November 2026 to January 2027
- Work in the ERP
- 5 tasks, about 3 h 20 min
Who hands what to whom
Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.
Comes to you
ArchitectLeads the design team- Concept drawingsTask 1
- Option B: steel frame, rendered wallsTask 4
- Budget letterFrom the Trust's board
- Total project budget, VAT inTask 5
YouCost consultant, working for the clientGoes from you
- Order of cost estimateTask 1
- Cost plan 1 and the cost limitTask 3
- Saving from option BTask 4
- Cost plan 2 against the budgetTask 5
The health trustClient, sets the budget
The project and the people are fictional. Portraits are generated.
Your route through the job
One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.
Order of cost
Task 1 · 40 min
GIFA and the order-of-cost estimate
- You produce
- Floor area (GIFA, measured inside the outer walls) and the first estimate
- Document
- Concept drawings, a benchmark rate and price indices
- In the ERP
- Bill of Quantities
Cost plan 1
Task 2 · 50 min
The elemental cost plan
- You produce
- Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
- Document
- Element unit quantities and rates
- In the ERP
- Bill of Quantities, Cost Breakdown
Cost plan 1
Task 3 · 40 min
From building works to the cost limit
- You produce
- The cost limit at the tender date
- Document
- Allowances and the inflation forecast
- In the ERP
- Bill of Quantities, Markups
Cost plan 2
Task 4 · 40 min
Value engineering: steel frame and rendered walls
- You produce
- The saving from option B, after the redesign fee
- Document
- Option B rates from the design team
- In the ERP
- Bill of Quantities
Cost plan 2
Task 5 · 30 min
Reconcile cost plan 2 to the budget
- You produce
- The variance to budget and the cost per m²
- Document
- The Trust's budget letter
- In the ERP
- Bill of Quantities, Cost Breakdown
How a floor area becomes a cost limit
Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.
Blue is what the task adds; grey is carried over from before.
In short. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.