Uvod u tečaj · 3 min
Planiranje troškova po elementima u fazi idejnog rješenja (UK, RICS NRM 1)
You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.
Izmišljeni projekt- Building
- Three storeys, atrium and an enclosed roof plant room
- Rules
- RICS NRM 1, the UK rules for early cost estimates and cost plans
- Story
- Concept design, November 2026 to January 2027
- Rad u ERP-u
- Zadataka: 5, oko 3 h 20 min
Tko kome što predaje
Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.
Dolazi vama
ArchitectLeads the design team- Concept drawingsZadatak 1
- Option B: steel frame, rendered wallsZadatak 4
- Budget letterFrom the Trust's board
- Total project budget, VAT inZadatak 5
ViCost consultant, working for the clientOdlazi od vas
- Order of cost estimateZadatak 1
- Cost plan 1 and the cost limitZadatak 3
- Saving from option BZadatak 4
- Cost plan 2 against the budgetZadatak 5
The health trustClient, sets the budget
Projekt i osobe su izmišljeni. Portreti su generirani.
Vaš put kroz projekt
One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.
Order of cost
Zadatak 1 · 40 min
GIFA i okvirna procjena troškova
- Vaš rezultat
- Floor area (GIFA, measured inside the outer walls) and the first estimate
- Dokument
- Concept drawings, a benchmark rate and price indices
- U ERP-u
- Bill of Quantities
Cost plan 1
Zadatak 2 · 50 min
Plan troškova po elementima
- Vaš rezultat
- Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
- Dokument
- Element unit quantities and rates
- U ERP-u
- Bill of Quantities, Cost Breakdown
Cost plan 1
Zadatak 3 · 40 min
Od građevinskih radova do granice troškova
- Vaš rezultat
- The cost limit at the tender date
- Dokument
- Allowances and the inflation forecast
- U ERP-u
- Bill of Quantities, Markups
Cost plan 2
Zadatak 4 · 40 min
Vrijednosno inženjerstvo: čelična konstrukcija i žbukani zidovi
- Vaš rezultat
- The saving from option B, after the redesign fee
- Dokument
- Option B rates from the design team
- U ERP-u
- Bill of Quantities
Cost plan 2
Zadatak 5 · 30 min
Usklađivanje plana troškova 2 s proračunom
- Vaš rezultat
- The variance to budget and the cost per m²
- Dokument
- The Trust's budget letter
- U ERP-u
- Bill of Quantities, Cost Breakdown
How a floor area becomes a cost limit
Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.