OpenConstruction Academy
Prijava / Registracija
HR

Uvod u tečaj · 3 min

Planiranje troškova po elementima u fazi idejnog rješenja (UK, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

Započni zadatak 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Izmišljeni projekt
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
Rad u ERP-u
Zadataka: 5, oko 3 h 20 min

Tko kome što predaje

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Dolazi vama

  • ArchitectLeads the design team
    • Concept drawingsZadatak 1
    • Option B: steel frame, rendered wallsZadatak 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inZadatak 5
ViCost consultant, working for the client

Odlazi od vas

    • Order of cost estimateZadatak 1
    • Cost plan 1 and the cost limitZadatak 3
    • Saving from option BZadatak 4
    • Cost plan 2 against the budgetZadatak 5
    The health trustClient, sets the budget

Projekt i osobe su izmišljeni. Portreti su generirani.

Vaš put kroz projekt

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Zadatak 1 · 40 min

    GIFA i okvirna procjena troškova

    Vaš rezultat
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Dokument
    Concept drawings, a benchmark rate and price indices
    U ERP-u
    Bill of Quantities
  2. Cost plan 1

    Zadatak 2 · 50 min

    Plan troškova po elementima

    Vaš rezultat
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Dokument
    Element unit quantities and rates
    U ERP-u
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Zadatak 3 · 40 min

    Od građevinskih radova do granice troškova

    Vaš rezultat
    The cost limit at the tender date
    Dokument
    Allowances and the inflation forecast
    U ERP-u
    Bill of Quantities, Markups
  4. Cost plan 2

    Zadatak 4 · 40 min

    Vrijednosno inženjerstvo: čelična konstrukcija i žbukani zidovi

    Vaš rezultat
    The saving from option B, after the redesign fee
    Dokument
    Option B rates from the design team
    U ERP-u
    Bill of Quantities
  5. Cost plan 2

    Zadatak 5 · 30 min

    Usklađivanje plana troškova 2 s proračunom

    Vaš rezultat
    The variance to budget and the cost per m²
    Dokument
    The Trust's budget letter
    U ERP-u
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Zadatak 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Zadatak 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Zadatak 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Zadatak 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Zadatak 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.