Въведение в курса · 3 мин

Планиране на разходите по елементи на концептуален етап (UK, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

Започнете задача 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Измислен проект
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
Работа в ERP
Задачи: 5, около 3 ч 20 мин

Кой какво предава на кого

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Идва при вас

  • ArchitectLeads the design team
    • Concept drawingsЗадача 1
    • Option B: steel frame, rendered wallsЗадача 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inЗадача 5
ВиеCost consultant, working for the client

Тръгва от вас

    • Order of cost estimateЗадача 1
    • Cost plan 1 and the cost limitЗадача 3
    • Saving from option BЗадача 4
    • Cost plan 2 against the budgetЗадача 5
    The health trustClient, sets the budget

Проектът и хората са измислени. Портретите са генерирани.

Вашият път през проекта

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Задача 1 · 40 мин

    GIFA и предварителната оценка на разходите

    Вашият резултат
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Документ
    Concept drawings, a benchmark rate and price indices
    В ERP
    Bill of Quantities
  2. Cost plan 1

    Задача 2 · 50 мин

    Елементният стойностен план

    Вашият резултат
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Документ
    Element unit quantities and rates
    В ERP
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Задача 3 · 40 мин

    От строителните работи до лимита на разходите

    Вашият резултат
    The cost limit at the tender date
    Документ
    Allowances and the inflation forecast
    В ERP
    Bill of Quantities, Markups
  4. Cost plan 2

    Задача 4 · 40 мин

    Оптимизация на разходите: стоманена конструкция и измазани стени

    Вашият резултат
    The saving from option B, after the redesign fee
    Документ
    Option B rates from the design team
    В ERP
    Bill of Quantities
  5. Cost plan 2

    Задача 5 · 30 мин

    Равнение на стойностен план 2 спрямо бюджета

    Вашият резултат
    The variance to budget and the cost per m²
    Документ
    The Trust's budget letter
    В ERP
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Задача 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Задача 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Задача 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Задача 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Задача 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.