Въведение в курса · 3 мин
Планиране на разходите по елементи на концептуален етап (UK, RICS NRM 1)
You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.
Измислен проект- Building
- Three storeys, atrium and an enclosed roof plant room
- Rules
- RICS NRM 1, the UK rules for early cost estimates and cost plans
- Story
- Concept design, November 2026 to January 2027
- Работа в ERP
- Задачи: 5, около 3 ч 20 мин
Кой какво предава на кого
Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.
Идва при вас
ArchitectLeads the design team- Concept drawingsЗадача 1
- Option B: steel frame, rendered wallsЗадача 4
- Budget letterFrom the Trust's board
- Total project budget, VAT inЗадача 5
ВиеCost consultant, working for the clientТръгва от вас
- Order of cost estimateЗадача 1
- Cost plan 1 and the cost limitЗадача 3
- Saving from option BЗадача 4
- Cost plan 2 against the budgetЗадача 5
The health trustClient, sets the budget
Проектът и хората са измислени. Портретите са генерирани.
Вашият път през проекта
One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.
Order of cost
Задача 1 · 40 мин
GIFA и предварителната оценка на разходите
- Вашият резултат
- Floor area (GIFA, measured inside the outer walls) and the first estimate
- Документ
- Concept drawings, a benchmark rate and price indices
- В ERP
- Bill of Quantities
Cost plan 1
Задача 2 · 50 мин
Елементният стойностен план
- Вашият резултат
- Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
- Документ
- Element unit quantities and rates
- В ERP
- Bill of Quantities, Cost Breakdown
Cost plan 1
Задача 3 · 40 мин
От строителните работи до лимита на разходите
- Вашият резултат
- The cost limit at the tender date
- Документ
- Allowances and the inflation forecast
- В ERP
- Bill of Quantities, Markups
Cost plan 2
Задача 4 · 40 мин
Оптимизация на разходите: стоманена конструкция и измазани стени
- Вашият резултат
- The saving from option B, after the redesign fee
- Документ
- Option B rates from the design team
- В ERP
- Bill of Quantities
Cost plan 2
Задача 5 · 30 мин
Равнение на стойностен план 2 спрямо бюджета
- Вашият резултат
- The variance to budget and the cost per m²
- Документ
- The Trust's budget letter
- В ERP
- Bill of Quantities, Cost Breakdown
How a floor area becomes a cost limit
Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.