Kursuse sissejuhatus · 3 min

Elementidepõhine kuluplaneerimine kontseptsioonietapis (Ühendkuningriik, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

Alusta ülesannet 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Väljamõeldud projekt
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
Töö ERP-s
Ülesandeid 5, umbes 3 h 20 min

Kes annab kellele mida

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Tuleb sinule

  • ArchitectLeads the design team
    • Concept drawingsÜlesanne 1
    • Option B: steel frame, rendered wallsÜlesanne 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inÜlesanne 5
SinaCost consultant, working for the client

Läheb sinult

    • Order of cost estimateÜlesanne 1
    • Cost plan 1 and the cost limitÜlesanne 3
    • Saving from option BÜlesanne 4
    • Cost plan 2 against the budgetÜlesanne 5
    The health trustClient, sets the budget

Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.

Sinu tee läbi projekti

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Ülesanne 1 · 40 min

    GIFA ja suurusjärgu hinnang

    Sinu tulemus
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Dokument
    Concept drawings, a benchmark rate and price indices
    ERP-s
    Bill of Quantities
  2. Cost plan 1

    Ülesanne 2 · 50 min

    Elementidepõhine kuluplaan

    Sinu tulemus
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Dokument
    Element unit quantities and rates
    ERP-s
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Ülesanne 3 · 40 min

    Ehitustöödest kulupiiranguni

    Sinu tulemus
    The cost limit at the tender date
    Dokument
    Allowances and the inflation forecast
    ERP-s
    Bill of Quantities, Markups
  4. Cost plan 2

    Ülesanne 4 · 40 min

    Väärtusinseneeria: terskarkass ja krohvitud seinad

    Sinu tulemus
    The saving from option B, after the redesign fee
    Dokument
    Option B rates from the design team
    ERP-s
    Bill of Quantities
  5. Cost plan 2

    Ülesanne 5 · 30 min

    Kuluplaani 2 ühtlustamine eelarvega

    Sinu tulemus
    The variance to budget and the cost per m²
    Dokument
    The Trust's budget letter
    ERP-s
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Ülesanne 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Ülesanne 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Ülesanne 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Ülesanne 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Ülesanne 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Sinine on see, mida ülesanne lisab; hall tuleb varasemast.

Lühidalt. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.