Kursuse sissejuhatus · 3 min
Elementidepõhine kuluplaneerimine kontseptsioonietapis (Ühendkuningriik, RICS NRM 1)
You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.
Väljamõeldud projekt- Building
- Three storeys, atrium and an enclosed roof plant room
- Rules
- RICS NRM 1, the UK rules for early cost estimates and cost plans
- Story
- Concept design, November 2026 to January 2027
- Töö ERP-s
- Ülesandeid 5, umbes 3 h 20 min
Kes annab kellele mida
Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.
Tuleb sinule
ArchitectLeads the design team- Concept drawingsÜlesanne 1
- Option B: steel frame, rendered wallsÜlesanne 4
- Budget letterFrom the Trust's board
- Total project budget, VAT inÜlesanne 5
SinaCost consultant, working for the clientLäheb sinult
- Order of cost estimateÜlesanne 1
- Cost plan 1 and the cost limitÜlesanne 3
- Saving from option BÜlesanne 4
- Cost plan 2 against the budgetÜlesanne 5
The health trustClient, sets the budget
Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.
Sinu tee läbi projekti
One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.
Order of cost
Ülesanne 1 · 40 min
GIFA ja suurusjärgu hinnang
- Sinu tulemus
- Floor area (GIFA, measured inside the outer walls) and the first estimate
- Dokument
- Concept drawings, a benchmark rate and price indices
- ERP-s
- Bill of Quantities
Cost plan 1
Ülesanne 2 · 50 min
Elementidepõhine kuluplaan
- Sinu tulemus
- Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
- Dokument
- Element unit quantities and rates
- ERP-s
- Bill of Quantities, Cost Breakdown
Cost plan 1
Ülesanne 3 · 40 min
Ehitustöödest kulupiiranguni
- Sinu tulemus
- The cost limit at the tender date
- Dokument
- Allowances and the inflation forecast
- ERP-s
- Bill of Quantities, Markups
Cost plan 2
Ülesanne 4 · 40 min
Väärtusinseneeria: terskarkass ja krohvitud seinad
- Sinu tulemus
- The saving from option B, after the redesign fee
- Dokument
- Option B rates from the design team
- ERP-s
- Bill of Quantities
Cost plan 2
Ülesanne 5 · 30 min
Kuluplaani 2 ühtlustamine eelarvega
- Sinu tulemus
- The variance to budget and the cost per m²
- Dokument
- The Trust's budget letter
- ERP-s
- Bill of Quantities, Cost Breakdown
How a floor area becomes a cost limit
Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.