Úvod do kurzu · 3 min

Prvkové plánování nákladů ve fázi konceptu (UK, RICS NRM 1)

You are the cost consultant for the client, an NHS Trust, building a new health centre in England. At the start there are only sketches, but the client must know what the building will cost before it commits. In five tasks you turn the concept design into a cost limit, test a cheaper frame and outer walls, and report the result against the client's budget.

Začít úlohu 1

A cleared, muddy site behind green hoarding in an English town, with a site cabin, setting-out pegs and two people in high-visibility jackets studying drawings.Smyšlený projekt
Larkmoor Health CentreThree-storey health centre, England
Building
Three storeys, atrium and an enclosed roof plant room
Rules
RICS NRM 1, the UK rules for early cost estimates and cost plans
Story
Concept design, November 2026 to January 2027
Práce v ERP
Úlohy: 5, asi 3 h 20 min

Kdo komu co předává

Nothing is built yet. Everything that passes between you and the others is a drawing, a figure or a letter.

Přichází k vám

  • ArchitectLeads the design team
    • Concept drawingsÚloha 1
    • Option B: steel frame, rendered wallsÚloha 4
  • Budget letterFrom the Trust's board
    • Total project budget, VAT inÚloha 5
VyCost consultant, working for the client

Odchází od vás

    • Order of cost estimateÚloha 1
    • Cost plan 1 and the cost limitÚloha 3
    • Saving from option BÚloha 4
    • Cost plan 2 against the budgetÚloha 5
    The health trustClient, sets the budget

Projekt i lidé jsou smyšlení. Portréty jsou vygenerované.

Vaše cesta zakázkou

One task from a single rate, two to build the first cost plan, two to change it and report. Start with task 1: in the Bill of Quantities you measure the floor area (GIFA) and multiply it by a rate from similar buildings.

  1. Order of cost

    Úloha 1 · 40 min

    GIFA a orientační odhad nákladů

    Výstup
    Floor area (GIFA, measured inside the outer walls) and the first estimate
    Dokument
    Concept drawings, a benchmark rate and price indices
    V ERP
    Bill of Quantities
  2. Cost plan 1

    Úloha 2 · 50 min

    Prvkový plán nákladů

    Výstup
    Elements 1 to 8 (frame, roof, walls and so on) and the cost check per m²
    Dokument
    Element unit quantities and rates
    V ERP
    Bill of Quantities, Cost Breakdown
  3. Cost plan 1

    Úloha 3 · 40 min

    Od stavebních prací k nákladovému limitu

    Výstup
    The cost limit at the tender date
    Dokument
    Allowances and the inflation forecast
    V ERP
    Bill of Quantities, Markups
  4. Cost plan 2

    Úloha 4 · 40 min

    Hodnotové inženýrství: ocelový skelet a omítnuté stěny

    Výstup
    The saving from option B, after the redesign fee
    Dokument
    Option B rates from the design team
    V ERP
    Bill of Quantities
  5. Cost plan 2

    Úloha 5 · 30 min

    Porovnání plánu nákladů 2 s rozpočtem

    Výstup
    The variance to budget and the cost per m²
    Dokument
    The Trust's budget letter
    V ERP
    Bill of Quantities, Cost Breakdown

How a floor area becomes a cost limit

Each column is one task. The grey part is carried from the task before, the coloured part is what that task adds.

GIFA × adjusted rate
Úloha 1Order of costFloor area times a cost per m² from similar buildings, moved to your date and place. One number, from the top down.
Elements 1 to 8
Úloha 2Elemental planThe same building priced element by element (frame, roof, walls), then checked against the first estimate.
InflationRiskPreliminaries, overheads and profitBuilding works
Úloha 3Cost limitPreliminaries, overheads and profit, risk and inflation, in that order, each on its own base.
SavingInflationRiskMark-upsBuilding works, option B
Úloha 4Option BA cheaper frame and envelope. The saving runs through every percentage row.
VarianceCost plan 2
Úloha 5Against the budgetVAT, fees and other costs out of the budget, then the plan is compared with what is left.

Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.

Stručně. Measure GIFA inside the walls. Price each element on its own measure. Add the percentage rows in NRM 1 order, each once. Compare like with like.