The interim invoice (Abschlagsrechnung) and the Deckungsrücklass
A conto-faktura (Abschlagsrechnung) med dekningstilbakehold
Etter denne leksjonen kan du
Build an interim invoice from measured progress at contract prices.
Withhold the Deckungsrücklass from the net invoice amount.
Add 20 % USt and know why reverse charge does not apply to a municipality's school.
1 / 3
Paid as the work goes
Under ÖNORM B 2110 the contractor may invoice progress in interim invoices (Abschlagsrechnungen): quantities done to date at the contract unit prices. An interim invoice falls due 30 days after it is received (8.4.1.1). Changes still under review, such as an unagreed claim, stay out until they are agreed.
Eksempel. Interim invoices are payments on account. The final invoice settles everything.
2 / 3
The Deckungsrücklass
The client withholds a share of each interim invoice as cover against overpayment: the Deckungsrücklass. This contract sets 5 % of the net invoice amount, which is the ÖNORM B 2110 figure. It is released with the final invoice, when the real quantities are known.
Eksempel. Net 84,250.00 €: Deckungsrücklass 4,212.50 €.
3 / 3
USt and reverse charge
Building work is taxed at 20 % USt (UStG 1994, § 10). Reverse charge (§ 19 Abs. 1a) moves the tax to the recipient only if the recipient is itself a business commissioned with the building work or usually provides building work, such as a main contractor buying from a subcontractor. A municipality building a school is neither, so the contractor invoices 20 % USt. The Rücklass is taken on the net amount and deducted from the gross.
Eksempel. Payment = net + 20 % USt − Deckungsrücklass.
Net invoice amount€84,250.00
USt 20 %€16,850.00
Deckungsrücklass 5 % of net−€4,212.50
Payment€96,887.50
Interim invoice 1
At month end the measured progress at contract prices is known. The client is a municipality.
Ikke i målestokk
Oppgaven
Work done to date at contract unit prices, net: €84,250.00. No earlier invoice.
Deckungsrücklass 5 % of the net invoice amount. USt 20 %; no reverse charge.
Trinn 1 av 3
Deckungsrücklass
5 % of the net amount. What is withheld?
Hint: Net × 5 %.
€84,250.00 × 5 % = €4,212.50.
Trinn 2 av 3
Gross with USt
Add 20 % USt. What is the gross?
Hint: Net × 1.20.
€84,250.00 × 1.20 = €101,100.00.
1 Net
2 USt 20 %
3 Rücklass
4 Payment
1 Net
2 USt 20 %
3 Rücklass
4 Payment
Trinn 3 av 3
Payment
Gross less the Deckungsrücklass. What is paid?
Hint: The Rücklass comes off the gross, computed on the net.
€101,100.00 − €4,212.50 = €96,887.50.
Kort sagt. Net progress at contract prices, Rücklass on the net, USt on the net, Rücklass off the gross.
Test deg selv
Spørsmål 1 av 3
Net interim invoice 60,000.00 €, Deckungsrücklass 5 % of net, USt 20 %. What is the payment?
72,000.00 − 3,000.00 = €69,000.00.
Spørsmål 2 av 3
Does reverse charge apply when a builder invoices a municipality for a school extension?
Only if the recipient itself provides building work or was commissioned with it.
Right. UStG § 19 Abs. 1a.
There is no threshold in that rule.
Spørsmål 3 av 3
An unagreed claim for additional cost exists. Does it go into the interim invoice?