Read a bar mark: number, size, shape code and the dimensions A, B, C.
Work out a cut length from outside dimensions by taking back what each bend uses.
Size a link inside the cover and count links zone by zone.
1 / 6
A schedule line describes one bar mark
Mark: the bar's name on the drawing, such as 01.
Number and size: 3 T25 is three 25 mm ribbed bars.
Shape code and dimensions: how the bar is bent, and how big.
The bar bending schedule is a table, one row per mark. The fabricator cuts and bends from it, and you measure from it. BS 8666 sets the shape codes, the dimensions and the minimum bends.
2 / 6
Four shape codes cover most of a beam
Each code has its own length formula.
The drawing gives the dimensions; the formula gives the length to cut.
Read the code before you read the numbers.
Shape 00Straight bar, one dimension A
Shape 11One 90° bend: A and B
Shape 21Two 90° bends, a U: A, B and C
Shape 51Closed link with two hooks
These are the shapes in your task. BS 8666 lists many more, each drawn with its dimensions lettered A, B, C, D.
3 / 6
Outside dimensions overstate the bar
A, B and C are measured to the outer face of the bar.
A bent bar runs round a curve, not into a sharp corner.
So each bend takes some length back.
A, first leg (mm)900
B, second leg (mm)300
A + B, round the outside (mm)1,200
Back for one bend, 0.5r + d (mm)16
Cut length of a T8, shape 11 (mm)1,184
For one 90° bend the formula takes back 0.5r + d. Shape 21 has two bends and takes back r + 2d. A shape 51 link takes back 2.5r + 5d.
4 / 6
The bend radius depends on the bar
A bar is bent round a pin, the former.
In this course the former is 4d up to T16 and 7d above it.
The radius r is half the former.
T8: former 4d, radius in mm
16
T40: former 7d, radius in mm
140
A thick bar needs a gentler bend, so its radius jumps above T16. That is why two bars with the same outside dimensions but different sizes have different cut lengths.
5 / 6
A link sits inside the cover
Cover is the concrete between the steel and the face.
Take the cover off both faces, in width and in depth.
The two hooks close the link inside the concrete.
Beam sectionWidth and depth, less the cover on each face
Hook tail C10d, never shorter than the minimum the rules set
Cut length2(A + B + C) − 2.5r − 5d
A link the size of the beam would touch the formwork. The hook tail is the straight end after the last bend: 10d, with a fixed minimum for thin bars that your task states.
6 / 6
Count links one zone at a time
Close spacing near the supports, wider in the middle.
In each zone: spaces rounded up, plus one link, so no gap is wider than drawn.
A link on the boundary of two zones is counted once.
One spacing over the whole beam either overcounts or undercounts. Draw the zones on a strip of paper and count the links you would fix.
Tastele cu săgeți sau glisare
Measure one beam
A different beam from your task, same rules. Type your answer first; a wrong guess costs nothing.
Nu este la scară
Problema
Beam 250 × 500 mm, 5,100 mm long. Cover 35 mm to the links and at the bar ends.
Top bar: T16, shape 21, legs A and C 350 mm. Links: T8, shape 51.
First link 50 mm from each end; 125 mm centres for 1,000 mm at each end, 250 mm centres between.
A + B + C, outside (mm)?
Two bends, r + 2d (mm)?
Cut length (mm)?
A + B + C, outside (mm)5,730
Two bends, r + 2d (mm)64
Cut length (mm)5,666
Pasul 1 din 4
Cut length of the top bar
B is the beam length less the end cover twice. A T16 bends on a 4d former, so r = 2d. What is the cut length in mm?
Indiciu: Add A, B and C, then take back r + 2d for the two bends.
B = 5,100 − 2 × 35 = 5,030. Round the outside: 350 + 5,030 + 350. Two bends on a 4d former take back r + 2d = 64 mm. Cut length 5,666 mm.
A, width inside the cover (mm)?
B, depth inside the cover (mm)?
C, hook tail (mm)?
Cut length (mm)?
A, width inside the cover (mm)180
B, depth inside the cover (mm)430
C, hook tail (mm)80
Cut length (mm)1,300
Pasul 2 din 4
Cut length of one link
A and B are the section less the cover on both faces. T8: tail 10d, r = 2d. What is the cut length in mm?
Indiciu: Width and depth each lose two covers. Then 2(A + B + C), less 2.5r + 5d.
A = 180, B = 430, tail C = 80. 2 × (180 + 430 + 80), less 2.5 × 16 + 5 × 8: 1,300 mm.
End zones, both
?
Middle zone
?
End zones, both
18
Middle zone
11
Pasul 3 din 4
How many links
Count each end zone, then the middle. A link on a zone boundary counts once. How many links?
Indiciu: End zone: {z} ÷ {se} spaces, plus one link. The middle starts and ends on links you already counted.
Each end zone: 8 spaces, 9 links, so 18 at both ends. The middle is 3,000 mm at 250: its spaces, rounded up, less the two boundary links already counted, leave 11. Total 29.
Links29
Cut length (mm)1,300
Total length?
Links29
Cut length (mm)1,300
Total length37.7 m
Pasul 4 din 4
Total length of the links
Number of links times the cut length, in metres. What goes in the bill?
Indiciu: Millimetres to metres: divide by a thousand.
29 × 1,300 mm = 37.7 m. The bill line is in metres; it becomes tonnes in task 3.
Pe scurt. Outside dimensions, less the bend deductions for the bar size, times the number of bars. Links inside the cover, counted zone by zone.
Verifică-te
Întrebarea 1 din 3
A T8 bar, shape 11, has A = 900 mm and B = 300 mm. The former is 4d, so r = 16 mm. Shape 11: L = A + B − 0.5r − d. What is the cut length in mm?
0.5 × 16 + 8 = 16 mm back. 900 + 300 − 16 = 1,184 mm.
Întrebarea 2 din 3
A zone of 2,250 mm has 150 mm centres, with a link at each end of the zone. How many links are in it?
That is the number of spaces. Add one link for the start of the row.
2,250 ÷ 150 = 15 spaces, plus one: 16 links. If the next zone starts on the last one, count it there only once.
One link too many: a row of 15 spaces has 16 links.
Întrebarea 3 din 3
Two top bars have the same outside dimensions. One is T16, the other T25. Which has the longer cut length?
The T25 bends on a 7d former, so each bend takes back more length.
A thicker bar has a larger bend radius, so it takes more back, not less.
The same outside dimensions do not mean the same bar: the bend deductions depend on d and r.