Introducere în curs · 3 min

Extras de armătură și tabel de fasonare (EAU, BS 8666)

You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.

Începe sarcina 1

A reinforced concrete residential frame under construction, with beam and slab reinforcement being fixed on the first floor.Proiect fictiv
Khor Sama ResidenceGround-plus-four residential block, UAE
Building
Ground plus four floors, concrete frame, flat slabs
Contract
FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
Story
March 2026 (Revision B) to June 2026 (Revision C)
Lucru în ERP
5 sarcini, circa 3 h 40 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • EngineerIssues drawings and instructions
    • Beam B7 detail, Rev BSarcina 1
    • Slab S3 detail, Rev BSarcina 2
    • Instruction EI 07, Rev CSarcina 5
  • Steel supplierQuotes and delivers the steel
    • Quotation per tonneSarcina 4
TuQuantity surveyor, main contractor

Pleacă de la tine

    • Measured bill linesSarcina 1
    • Package priceSarcina 4
    • Variation orderSarcina 5
    EmployerPrivate developer
    • Order quantity, waste inSarcina 3
    Your site teamPlaces the steel order

Proiectul și persoanele sunt fictive. Portretele sunt generate.

Traseul tău prin proiect

Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.

  1. Measure

    Sarcina 1 · 45 min

    Grinda B7: barele după codul de formă

    Produci
    Total length of each beam bar mark (each bar type on the drawing)
    Document
    Beam B7 detail, Revision B
    În ERP
    Bill of Quantities
  2. Measure

    Sarcina 2 · 45 min

    Placa S3: bare, petreceri și plasă

    Produci
    Slab bars with laps (overlaps at joints), and mesh sheets
    Document
    Slab S3 detail, Revision B
    În ERP
    Bill of Quantities
  3. Weigh

    Sarcina 3 · 40 min

    Mase, tonaj și comanda

    Produci
    Net tonnes by bar size, and the order
    Document
    Mass per metre, element counts
    În ERP
    Bill of Quantities
  4. Price

    Sarcina 4 · 40 min

    Evaluarea pachetului de armătură

    Produci
    A rate per net tonne, and the package price
    Document
    Supplier quotation and labour rates
    În ERP
    Bill of Quantities, Markups
  5. Change

    Sarcina 5 · 50 min

    Revizia C: remăsurarea modificării

    Produci
    The variation (priced change) for the new bar sizes
    Document
    Engineer's instruction EI 07, Revision C
    În ERP
    Variations

How a drawing becomes a price

Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.

Beam bars and links, in metres
Sarcina 1Cut lengthOutside dimensions, less what the bends take back, times the number of bars.
Slab bars and meshBeams
Sarcina 2Slab steelBars counted by spaces rounded up, plus one, a lap at each joint, mesh laid out sheet by sheet.
Overhead and profitNet tonnes at their rates
Sarcina 4Package priceNet tonnes times a rate built from supply, waste, cutting and fixing. One markup row on top.
Revision CPackage price
Sarcina 5VariationNew sizes go in, old sizes come out, both at the bill rates.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.