متره میلگرد و جدول خم میلگرد (امارات، BS 8666)

You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.

شروع تکلیف 1

A reinforced concrete residential frame under construction, with beam and slab reinforcement being fixed on the first floor.پروژهٔ خیالی
Khor Sama ResidenceGround-plus-four residential block, UAE
Building
Ground plus four floors, concrete frame, flat slabs
Contract
FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
Story
March 2026 (Revision B) to June 2026 (Revision C)
کار در ERP
5 تکلیف، حدود 3 ساعت 40 دقیقه

چه کسی چه چیزی به چه کسی می‌دهد

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

به شما می‌رسد

  • EngineerIssues drawings and instructions
    • Beam B7 detail, Rev Bتکلیف 1
    • Slab S3 detail, Rev Bتکلیف 2
    • Instruction EI 07, Rev Cتکلیف 5
  • Steel supplierQuotes and delivers the steel
    • Quotation per tonneتکلیف 4
شماQuantity surveyor, main contractor

از شما می‌رود

    • Measured bill linesتکلیف 1
    • Package priceتکلیف 4
    • Variation orderتکلیف 5
    EmployerPrivate developer
    • Order quantity, waste inتکلیف 3
    Your site teamPlaces the steel order

پروژه و افراد خیالی‌اند. چهره‌ها ساختگی هستند.

مسیر شما در پروژه

Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.

  1. Measure

    تکلیف 1 · 45 دقیقه

    تیر B7: میلگردها بر اساس کد شکل

    خروجی شما
    Total length of each beam bar mark (each bar type on the drawing)
    سند
    Beam B7 detail, Revision B
    در ERP
    Bill of Quantities
  2. Measure

    تکلیف 2 · 45 دقیقه

    دال S3: میلگرد، وصله و مش

    خروجی شما
    Slab bars with laps (overlaps at joints), and mesh sheets
    سند
    Slab S3 detail, Revision B
    در ERP
    Bill of Quantities
  3. Weigh

    تکلیف 3 · 40 دقیقه

    وزن‌ها، تناژ و سفارش

    خروجی شما
    Net tonnes by bar size, and the order
    سند
    Mass per metre, element counts
    در ERP
    Bill of Quantities
  4. Price

    تکلیف 4 · 40 دقیقه

    قیمت‌گذاری بسته‌ی میلگردگذاری

    خروجی شما
    A rate per net tonne, and the package price
    سند
    Supplier quotation and labour rates
    در ERP
    Bill of Quantities, Markups
  5. Change

    تکلیف 5 · 50 دقیقه

    بازنگری C: متره‌ی دوباره‌ی تغییر

    خروجی شما
    The variation (priced change) for the new bar sizes
    سند
    Engineer's instruction EI 07, Revision C
    در ERP
    Variations

How a drawing becomes a price

Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.

Beam bars and links, in metres
تکلیف 1Cut lengthOutside dimensions, less what the bends take back, times the number of bars.
Slab bars and meshBeams
تکلیف 2Slab steelBars counted by spaces rounded up, plus one, a lap at each joint, mesh laid out sheet by sheet.
Overhead and profitNet tonnes at their rates
تکلیف 4Package priceNet tonnes times a rate built from supply, waste, cutting and fixing. One markup row on top.
Revision CPackage price
تکلیف 5VariationNew sizes go in, old sizes come out, both at the bill rates.

آبی چیزی است که تکلیف اضافه می‌کند؛ خاکستری از مرحلهٔ قبل آمده است.

به‌طور خلاصه. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.