OpenConstruction Academy
Нэвтрэх / Бүртгүүлэх
MN

Сургалтын танилцуулга · 3 мин

Арматурын тооцоо ба нугалах хуваарь (АНЭУ, BS 8666)

You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.

1-р даалгаврыг эхлэх

A reinforced concrete residential frame under construction, with beam and slab reinforcement being fixed on the first floor.Зохиомол төсөл
Khor Sama ResidenceGround-plus-four residential block, UAE
Building
Ground plus four floors, concrete frame, flat slabs
Contract
FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
Story
March 2026 (Revision B) to June 2026 (Revision C)
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 3 цаг 40 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • EngineerIssues drawings and instructions
    • Beam B7 detail, Rev BДаалгавар 1
    • Slab S3 detail, Rev BДаалгавар 2
    • Instruction EI 07, Rev CДаалгавар 5
  • Steel supplierQuotes and delivers the steel
    • Quotation per tonneДаалгавар 4
ТаQuantity surveyor, main contractor

Танаас гардаг

    • Measured bill linesДаалгавар 1
    • Package priceДаалгавар 4
    • Variation orderДаалгавар 5
    EmployerPrivate developer
    • Order quantity, waste inДаалгавар 3
    Your site teamPlaces the steel order

Төсөл ба хүмүүс зохиомол. Хөрөг зургууд үүсгэгдсэн.

Төслөөр явах таны зам

Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.

  1. Measure

    Даалгавар 1 · 45 мин

    B7 дам нуруу: хэлбэрийн кодоор бар

    Үр дүн
    Total length of each beam bar mark (each bar type on the drawing)
    Баримт бичиг
    Beam B7 detail, Revision B
    ERP дээр
    Bill of Quantities
  2. Measure

    Даалгавар 2 · 45 мин

    S3 хавтан: бар, давхцал ба торон хуудас

    Үр дүн
    Slab bars with laps (overlaps at joints), and mesh sheets
    Баримт бичиг
    Slab S3 detail, Revision B
    ERP дээр
    Bill of Quantities
  3. Weigh

    Даалгавар 3 · 40 мин

    Жин, тонн ба захиалга

    Үр дүн
    Net tonnes by bar size, and the order
    Баримт бичиг
    Mass per metre, element counts
    ERP дээр
    Bill of Quantities
  4. Price

    Даалгавар 4 · 40 мин

    Арматурын багцыг үнэл

    Үр дүн
    A rate per net tonne, and the package price
    Баримт бичиг
    Supplier quotation and labour rates
    ERP дээр
    Bill of Quantities, Markups
  5. Change

    Даалгавар 5 · 50 мин

    Revision C: өөрчлөлтийг дахин хэмж

    Үр дүн
    The variation (priced change) for the new bar sizes
    Баримт бичиг
    Engineer's instruction EI 07, Revision C
    ERP дээр
    Variations

How a drawing becomes a price

Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.

Beam bars and links, in metres
Даалгавар 1Cut lengthOutside dimensions, less what the bends take back, times the number of bars.
Slab bars and meshBeams
Даалгавар 2Slab steelBars counted by spaces rounded up, plus one, a lap at each joint, mesh laid out sheet by sheet.
Overhead and profitNet tonnes at their rates
Даалгавар 4Package priceNet tonnes times a rate built from supply, waste, cutting and fixing. One markup row on top.
Revision CPackage price
Даалгавар 5VariationNew sizes go in, old sizes come out, both at the bill rates.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.