BS 8666 боюнча арматураны өлчөө жана бүгүү ведомосу (БАЭ)

You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.

1-тапшырманы баштоо

A reinforced concrete residential frame under construction, with beam and slab reinforcement being fixed on the first floor.Ойдон чыгарылган долбоор
Khor Sama ResidenceGround-plus-four residential block, UAE
Building
Ground plus four floors, concrete frame, flat slabs
Contract
FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
Story
March 2026 (Revision B) to June 2026 (Revision C)
ERPдеги иш
Тапшырмалар: 5, болжол менен 3 саат 40 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • EngineerIssues drawings and instructions
    • Beam B7 detail, Rev B1-тапшырма
    • Slab S3 detail, Rev B2-тапшырма
    • Instruction EI 07, Rev C5-тапшырма
  • Steel supplierQuotes and delivers the steel
    • Quotation per tonne4-тапшырма
СизQuantity surveyor, main contractor

Сизден кетет

    • Measured bill lines1-тапшырма
    • Package price4-тапшырма
    • Variation order5-тапшырма
    EmployerPrivate developer
    • Order quantity, waste in3-тапшырма
    Your site teamPlaces the steel order

Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.

Долбоор боюнча жолуңуз

Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.

  1. Measure

    1-тапшырма · 45 мүн

    B7 устуну: форма коду боюнча стерженьдер

    Натыйжа
    Total length of each beam bar mark (each bar type on the drawing)
    Документ
    Beam B7 detail, Revision B
    ERPде
    Bill of Quantities
  2. Measure

    2-тапшырма · 45 мүн

    S3 плитасы: стерженьдер, жалгамалар жана тор

    Натыйжа
    Slab bars with laps (overlaps at joints), and mesh sheets
    Документ
    Slab S3 detail, Revision B
    ERPде
    Bill of Quantities
  3. Weigh

    3-тапшырма · 40 мүн

    Салмак, тоннаж жана буйрутма

    Натыйжа
    Net tonnes by bar size, and the order
    Документ
    Mass per metre, element counts
    ERPде
    Bill of Quantities
  4. Price

    4-тапшырма · 40 мүн

    Арматура пакетин баалаңыз

    Натыйжа
    A rate per net tonne, and the package price
    Документ
    Supplier quotation and labour rates
    ERPде
    Bill of Quantities, Markups
  5. Change

    5-тапшырма · 50 мүн

    Revision C: өзгөрүүнү кайра өлчөңүз

    Натыйжа
    The variation (priced change) for the new bar sizes
    Документ
    Engineer's instruction EI 07, Revision C
    ERPде
    Variations

How a drawing becomes a price

Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.

Beam bars and links, in metres
1-тапшырмаCut lengthOutside dimensions, less what the bends take back, times the number of bars.
Slab bars and meshBeams
2-тапшырмаSlab steelBars counted by spaces rounded up, plus one, a lap at each joint, mesh laid out sheet by sheet.
Overhead and profitNet tonnes at their rates
4-тапшырмаPackage priceNet tonnes times a rate built from supply, waste, cutting and fixing. One markup row on top.
Revision CPackage price
5-тапшырмаVariationNew sizes go in, old sizes come out, both at the bill rates.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.