Introduktion till kursen · 3 min
Armeringsmängdning och böjningslista (Förenade Arabemiraten, BS 8666)
You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.
Fiktivt projekt- Building
- Ground plus four floors, concrete frame, flat slabs
- Contract
- FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
- Story
- March 2026 (Revision B) to June 2026 (Revision C)
- Arbete i ERP
- 5 uppgifter, cirka 3 h 40 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
EngineerIssues drawings and instructions- Beam B7 detail, Rev BUppgift 1
- Slab S3 detail, Rev BUppgift 2
- Instruction EI 07, Rev CUppgift 5
Steel supplierQuotes and delivers the steel- Quotation per tonneUppgift 4
DuQuantity surveyor, main contractorGår från dig
- Measured bill linesUppgift 1
- Package priceUppgift 4
- Variation orderUppgift 5
- Order quantity, waste inUppgift 3
Projektet och personerna är fiktiva. Porträtten är genererade.
Din väg genom projektet
Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.
Measure
Uppgift 1 · 45 min
Balk B7: stänger efter formkod
- Du tar fram
- Total length of each beam bar mark (each bar type on the drawing)
- Dokument
- Beam B7 detail, Revision B
- I ERP
- Bill of Quantities
Measure
Uppgift 2 · 45 min
Bjälklag S3: stänger, skarvar och nät
- Du tar fram
- Slab bars with laps (overlaps at joints), and mesh sheets
- Dokument
- Slab S3 detail, Revision B
- I ERP
- Bill of Quantities
Weigh
Uppgift 3 · 40 min
Vikter, tonnage och beställningen
- Du tar fram
- Net tonnes by bar size, and the order
- Dokument
- Mass per metre, element counts
- I ERP
- Bill of Quantities
Price
Uppgift 4 · 40 min
Prissätt armeringspaketet
- Du tar fram
- A rate per net tonne, and the package price
- Dokument
- Supplier quotation and labour rates
- I ERP
- Bill of Quantities, Markups
Change
Uppgift 5 · 50 min
Revision C: mät om ändringen
- Du tar fram
- The variation (priced change) for the new bar sizes
- Dokument
- Engineer's instruction EI 07, Revision C
- I ERP
- Variations
How a drawing becomes a price
Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.