Introduktion till kursen · 3 min

Armeringsmängdning och böjningslista (Förenade Arabemiraten, BS 8666)

You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.

Starta uppgift 1

A reinforced concrete residential frame under construction, with beam and slab reinforcement being fixed on the first floor.Fiktivt projekt
Khor Sama ResidenceGround-plus-four residential block, UAE
Building
Ground plus four floors, concrete frame, flat slabs
Contract
FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
Story
March 2026 (Revision B) to June 2026 (Revision C)
Arbete i ERP
5 uppgifter, cirka 3 h 40 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • EngineerIssues drawings and instructions
    • Beam B7 detail, Rev BUppgift 1
    • Slab S3 detail, Rev BUppgift 2
    • Instruction EI 07, Rev CUppgift 5
  • Steel supplierQuotes and delivers the steel
    • Quotation per tonneUppgift 4
DuQuantity surveyor, main contractor

Går från dig

    • Measured bill linesUppgift 1
    • Package priceUppgift 4
    • Variation orderUppgift 5
    EmployerPrivate developer
    • Order quantity, waste inUppgift 3
    Your site teamPlaces the steel order

Projektet och personerna är fiktiva. Porträtten är genererade.

Din väg genom projektet

Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.

  1. Measure

    Uppgift 1 · 45 min

    Balk B7: stänger efter formkod

    Du tar fram
    Total length of each beam bar mark (each bar type on the drawing)
    Dokument
    Beam B7 detail, Revision B
    I ERP
    Bill of Quantities
  2. Measure

    Uppgift 2 · 45 min

    Bjälklag S3: stänger, skarvar och nät

    Du tar fram
    Slab bars with laps (overlaps at joints), and mesh sheets
    Dokument
    Slab S3 detail, Revision B
    I ERP
    Bill of Quantities
  3. Weigh

    Uppgift 3 · 40 min

    Vikter, tonnage och beställningen

    Du tar fram
    Net tonnes by bar size, and the order
    Dokument
    Mass per metre, element counts
    I ERP
    Bill of Quantities
  4. Price

    Uppgift 4 · 40 min

    Prissätt armeringspaketet

    Du tar fram
    A rate per net tonne, and the package price
    Dokument
    Supplier quotation and labour rates
    I ERP
    Bill of Quantities, Markups
  5. Change

    Uppgift 5 · 50 min

    Revision C: mät om ändringen

    Du tar fram
    The variation (priced change) for the new bar sizes
    Dokument
    Engineer's instruction EI 07, Revision C
    I ERP
    Variations

How a drawing becomes a price

Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.

Beam bars and links, in metres
Uppgift 1Cut lengthOutside dimensions, less what the bends take back, times the number of bars.
Slab bars and meshBeams
Uppgift 2Slab steelBars counted by spaces rounded up, plus one, a lap at each joint, mesh laid out sheet by sheet.
Overhead and profitNet tonnes at their rates
Uppgift 4Package priceNet tonnes times a rate built from supply, waste, cutting and fixing. One markup row on top.
Revision CPackage price
Uppgift 5VariationNew sizes go in, old sizes come out, both at the bill rates.

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.