Rebar takeoff and bar bending schedule (UAE, BS 8666)

You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.

Start task 1

A reinforced concrete residential frame under construction, with beam and slab reinforcement being fixed on the first floor.Fictional project
Khor Sama ResidenceGround-plus-four residential block, UAE
Building
Ground plus four floors, concrete frame, flat slabs
Contract
FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
Story
March 2026 (Revision B) to June 2026 (Revision C)
Work in the ERP
5 tasks, about 3 h 40 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • EngineerIssues drawings and instructions
    • Beam B7 detail, Rev BTask 1
    • Slab S3 detail, Rev BTask 2
    • Instruction EI 07, Rev CTask 5
  • Steel supplierQuotes and delivers the steel
    • Quotation per tonneTask 4
YouQuantity surveyor, main contractor

Goes from you

    • Measured bill linesTask 1
    • Package priceTask 4
    • Variation orderTask 5
    EmployerPrivate developer
    • Order quantity, waste inTask 3
    Your site teamPlaces the steel order

The project and the people are fictional. Portraits are generated.

Your route through the job

Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.

  1. Measure

    Task 1 · 45 min

    Beam B7: bars by shape code

    You produce
    Total length of each beam bar mark (each bar type on the drawing)
    Document
    Beam B7 detail, Revision B
    In the ERP
    Bill of Quantities
  2. Measure

    Task 2 · 45 min

    Slab S3: bars, laps and mesh

    You produce
    Slab bars with laps (overlaps at joints), and mesh sheets
    Document
    Slab S3 detail, Revision B
    In the ERP
    Bill of Quantities
  3. Weigh

    Task 3 · 40 min

    Weights, tonnage and the order

    You produce
    Net tonnes by bar size, and the order
    Document
    Mass per metre, element counts
    In the ERP
    Bill of Quantities
  4. Price

    Task 4 · 40 min

    Price the reinforcement package

    You produce
    A rate per net tonne, and the package price
    Document
    Supplier quotation and labour rates
    In the ERP
    Bill of Quantities, Markups
  5. Change

    Task 5 · 50 min

    Revision C: re-measure the change

    You produce
    The variation (priced change) for the new bar sizes
    Document
    Engineer's instruction EI 07, Revision C
    In the ERP
    Variations

How a drawing becomes a price

Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.

Beam bars and links, in metres
Task 1Cut lengthOutside dimensions, less what the bends take back, times the number of bars.
Slab bars and meshBeams
Task 2Slab steelBars counted by spaces rounded up, plus one, a lap at each joint, mesh laid out sheet by sheet.
Overhead and profitNet tonnes at their rates
Task 4Package priceNet tonnes times a rate built from supply, waste, cutting and fixing. One markup row on top.
Revision CPackage price
Task 5VariationNew sizes go in, old sizes come out, both at the bill rates.

Blue is what the task adds; grey is carried over from before.

In short. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.