Въведение в курса · 3 мин

Количества арматура и спецификация на огъване (ОАЕ, BS 8666)

You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.

Започнете задача 1

A reinforced concrete residential frame under construction, with beam and slab reinforcement being fixed on the first floor.Измислен проект
Khor Sama ResidenceGround-plus-four residential block, UAE
Building
Ground plus four floors, concrete frame, flat slabs
Contract
FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
Story
March 2026 (Revision B) to June 2026 (Revision C)
Работа в ERP
Задачи: 5, около 3 ч 40 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • EngineerIssues drawings and instructions
    • Beam B7 detail, Rev BЗадача 1
    • Slab S3 detail, Rev BЗадача 2
    • Instruction EI 07, Rev CЗадача 5
  • Steel supplierQuotes and delivers the steel
    • Quotation per tonneЗадача 4
ВиеQuantity surveyor, main contractor

Тръгва от вас

    • Measured bill linesЗадача 1
    • Package priceЗадача 4
    • Variation orderЗадача 5
    EmployerPrivate developer
    • Order quantity, waste inЗадача 3
    Your site teamPlaces the steel order

Проектът и хората са измислени. Портретите са генерирани.

Вашият път през проекта

Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.

  1. Measure

    Задача 1 · 45 мин

    Греда B7: пръти по код на форма

    Вашият резултат
    Total length of each beam bar mark (each bar type on the drawing)
    Документ
    Beam B7 detail, Revision B
    В ERP
    Bill of Quantities
  2. Measure

    Задача 2 · 45 мин

    Плоча S3: пръти, снаждания и мрежа

    Вашият резултат
    Slab bars with laps (overlaps at joints), and mesh sheets
    Документ
    Slab S3 detail, Revision B
    В ERP
    Bill of Quantities
  3. Weigh

    Задача 3 · 40 мин

    Тегла, тонаж и поръчката

    Вашият резултат
    Net tonnes by bar size, and the order
    Документ
    Mass per metre, element counts
    В ERP
    Bill of Quantities
  4. Price

    Задача 4 · 40 мин

    Остойностяване на пакета армировка

    Вашият резултат
    A rate per net tonne, and the package price
    Документ
    Supplier quotation and labour rates
    В ERP
    Bill of Quantities, Markups
  5. Change

    Задача 5 · 50 мин

    Revision C: ново измерване на промяната

    Вашият резултат
    The variation (priced change) for the new bar sizes
    Документ
    Engineer's instruction EI 07, Revision C
    В ERP
    Variations

How a drawing becomes a price

Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.

Beam bars and links, in metres
Задача 1Cut lengthOutside dimensions, less what the bends take back, times the number of bars.
Slab bars and meshBeams
Задача 2Slab steelBars counted by spaces rounded up, plus one, a lap at each joint, mesh laid out sheet by sheet.
Overhead and profitNet tonnes at their rates
Задача 4Package priceNet tonnes times a rate built from supply, waste, cutting and fixing. One markup row on top.
Revision CPackage price
Задача 5VariationNew sizes go in, old sizes come out, both at the bill rates.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.