Panimula ng kurso · 3 min

Rebar takeoff at bar bending schedule (UAE, BS 8666)

You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.

Simulan ang gawain 1

A reinforced concrete residential frame under construction, with beam and slab reinforcement being fixed on the first floor.Kathang-isip na proyekto
Khor Sama ResidenceGround-plus-four residential block, UAE
Building
Ground plus four floors, concrete frame, flat slabs
Contract
FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
Story
March 2026 (Revision B) to June 2026 (Revision C)
Trabaho sa ERP
5 gawain, mga 3 oras 40 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • EngineerIssues drawings and instructions
    • Beam B7 detail, Rev BGawain 1
    • Slab S3 detail, Rev BGawain 2
    • Instruction EI 07, Rev CGawain 5
  • Steel supplierQuotes and delivers the steel
    • Quotation per tonneGawain 4
IkawQuantity surveyor, main contractor

Lumalabas sa iyo

    • Measured bill linesGawain 1
    • Package priceGawain 4
    • Variation orderGawain 5
    EmployerPrivate developer
    • Order quantity, waste inGawain 3
    Your site teamPlaces the steel order

Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.

Ang ruta mo sa proyekto

Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.

  1. Measure

    Gawain 1 · 45 min

    Beam B7: mga bar ayon sa shape code

    Ang gagawin mo
    Total length of each beam bar mark (each bar type on the drawing)
    Dokumento
    Beam B7 detail, Revision B
    Sa ERP
    Bill of Quantities
  2. Measure

    Gawain 2 · 45 min

    Slab S3: mga bar, lap at mesh

    Ang gagawin mo
    Slab bars with laps (overlaps at joints), and mesh sheets
    Dokumento
    Slab S3 detail, Revision B
    Sa ERP
    Bill of Quantities
  3. Weigh

    Gawain 3 · 40 min

    Mga timbang, tonelada at ang order

    Ang gagawin mo
    Net tonnes by bar size, and the order
    Dokumento
    Mass per metre, element counts
    Sa ERP
    Bill of Quantities
  4. Price

    Gawain 4 · 40 min

    Presyuhan ang reinforcement package

    Ang gagawin mo
    A rate per net tonne, and the package price
    Dokumento
    Supplier quotation and labour rates
    Sa ERP
    Bill of Quantities, Markups
  5. Change

    Gawain 5 · 50 min

    Rebisyon C: sukatin muli ang pagbabago

    Ang gagawin mo
    The variation (priced change) for the new bar sizes
    Dokumento
    Engineer's instruction EI 07, Revision C
    Sa ERP
    Variations

How a drawing becomes a price

Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.

Beam bars and links, in metres
Gawain 1Cut lengthOutside dimensions, less what the bends take back, times the number of bars.
Slab bars and meshBeams
Gawain 2Slab steelBars counted by spaces rounded up, plus one, a lap at each joint, mesh laid out sheet by sheet.
Overhead and profitNet tonnes at their rates
Gawain 4Package priceNet tonnes times a rate built from supply, waste, cutting and fixing. One markup row on top.
Revision CPackage price
Gawain 5VariationNew sizes go in, old sizes come out, both at the bill rates.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.