Armatuuri mahuarvutus ja painutusnimekiri (AÜE, BS 8666)
You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.
Väljamõeldud projekt- Building
- Ground plus four floors, concrete frame, flat slabs
- Contract
- FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
- Story
- March 2026 (Revision B) to June 2026 (Revision C)
- Töö ERP-s
- Ülesandeid 5, umbes 3 h 40 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
EngineerIssues drawings and instructions- Beam B7 detail, Rev BÜlesanne 1
- Slab S3 detail, Rev BÜlesanne 2
- Instruction EI 07, Rev CÜlesanne 5
Steel supplierQuotes and delivers the steel- Quotation per tonneÜlesanne 4
SinaQuantity surveyor, main contractorLäheb sinult
- Measured bill linesÜlesanne 1
- Package priceÜlesanne 4
- Variation orderÜlesanne 5
- Order quantity, waste inÜlesanne 3
Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.
Sinu tee läbi projekti
Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.
Measure
Ülesanne 1 · 45 min
Tala B7: vardad kujukoodi järgi
- Sinu tulemus
- Total length of each beam bar mark (each bar type on the drawing)
- Dokument
- Beam B7 detail, Revision B
- ERP-s
- Bill of Quantities
Measure
Ülesanne 2 · 45 min
Plaat S3: vardad, ülekatted ja võrk
- Sinu tulemus
- Slab bars with laps (overlaps at joints), and mesh sheets
- Dokument
- Slab S3 detail, Revision B
- ERP-s
- Bill of Quantities
Weigh
Ülesanne 3 · 40 min
Kaalud, tonnaaž ja tellimus
- Sinu tulemus
- Net tonnes by bar size, and the order
- Dokument
- Mass per metre, element counts
- ERP-s
- Bill of Quantities
Price
Ülesanne 4 · 40 min
Armatuuripaketi hindamine
- Sinu tulemus
- A rate per net tonne, and the package price
- Dokument
- Supplier quotation and labour rates
- ERP-s
- Bill of Quantities, Markups
Change
Ülesanne 5 · 50 min
Revision C: muudatuse uuesti mõõtmine
- Sinu tulemus
- The variation (priced change) for the new bar sizes
- Dokument
- Engineer's instruction EI 07, Revision C
- ERP-s
- Variations
How a drawing becomes a price
Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.