Introduktion til kurset · 3 min
Armeringsmængder og bøjningsliste (Forenede Arabiske Emirater, BS 8666)
You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.
Fiktivt projekt- Building
- Ground plus four floors, concrete frame, flat slabs
- Contract
- FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
- Story
- March 2026 (Revision B) to June 2026 (Revision C)
- Arbejde i ERP
- 5 opgaver, cirka 3 t 40 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
EngineerIssues drawings and instructions- Beam B7 detail, Rev BOpgave 1
- Slab S3 detail, Rev BOpgave 2
- Instruction EI 07, Rev COpgave 5
Steel supplierQuotes and delivers the steel- Quotation per tonneOpgave 4
DigQuantity surveyor, main contractorGår fra dig
- Measured bill linesOpgave 1
- Package priceOpgave 4
- Variation orderOpgave 5
- Order quantity, waste inOpgave 3
Projektet og personerne er fiktive. Portrætterne er genererede.
Din vej gennem sagen
Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.
Measure
Opgave 1 · 45 min
Bjælke B7: stænger efter formkode
- Du leverer
- Total length of each beam bar mark (each bar type on the drawing)
- Dokument
- Beam B7 detail, Revision B
- I ERP
- Bill of Quantities
Measure
Opgave 2 · 45 min
Dæk S3: stænger, overlæg og net
- Du leverer
- Slab bars with laps (overlaps at joints), and mesh sheets
- Dokument
- Slab S3 detail, Revision B
- I ERP
- Bill of Quantities
Weigh
Opgave 3 · 40 min
Vægte, tonnage og bestillingen
- Du leverer
- Net tonnes by bar size, and the order
- Dokument
- Mass per metre, element counts
- I ERP
- Bill of Quantities
Price
Opgave 4 · 40 min
Prissæt armeringspakken
- Du leverer
- A rate per net tonne, and the package price
- Dokument
- Supplier quotation and labour rates
- I ERP
- Bill of Quantities, Markups
Change
Opgave 5 · 50 min
Revision C: genopmål ændringen
- Du leverer
- The variation (priced change) for the new bar sizes
- Dokument
- Engineer's instruction EI 07, Revision C
- I ERP
- Variations
How a drawing becomes a price
Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.