OpenConstruction Academy
Prijava / Registracija
HR

Uvod u tečaj · 3 min

Iskaz količina armature i specifikacija savijanja (UAE, BS 8666)

You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.

Započni zadatak 1

A reinforced concrete residential frame under construction, with beam and slab reinforcement being fixed on the first floor.Izmišljeni projekt
Khor Sama ResidenceGround-plus-four residential block, UAE
Building
Ground plus four floors, concrete frame, flat slabs
Contract
FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
Story
March 2026 (Revision B) to June 2026 (Revision C)
Rad u ERP-u
Zadataka: 5, oko 3 h 40 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • EngineerIssues drawings and instructions
    • Beam B7 detail, Rev BZadatak 1
    • Slab S3 detail, Rev BZadatak 2
    • Instruction EI 07, Rev CZadatak 5
  • Steel supplierQuotes and delivers the steel
    • Quotation per tonneZadatak 4
ViQuantity surveyor, main contractor

Odlazi od vas

    • Measured bill linesZadatak 1
    • Package priceZadatak 4
    • Variation orderZadatak 5
    EmployerPrivate developer
    • Order quantity, waste inZadatak 3
    Your site teamPlaces the steel order

Projekt i osobe su izmišljeni. Portreti su generirani.

Vaš put kroz projekt

Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.

  1. Measure

    Zadatak 1 · 45 min

    Greda B7: šipke prema oznaci oblika

    Vaš rezultat
    Total length of each beam bar mark (each bar type on the drawing)
    Dokument
    Beam B7 detail, Revision B
    U ERP-u
    Bill of Quantities
  2. Measure

    Zadatak 2 · 45 min

    Ploča S3: šipke, preklopi i mreža

    Vaš rezultat
    Slab bars with laps (overlaps at joints), and mesh sheets
    Dokument
    Slab S3 detail, Revision B
    U ERP-u
    Bill of Quantities
  3. Weigh

    Zadatak 3 · 40 min

    Mase, tonaža i narudžba

    Vaš rezultat
    Net tonnes by bar size, and the order
    Dokument
    Mass per metre, element counts
    U ERP-u
    Bill of Quantities
  4. Price

    Zadatak 4 · 40 min

    Cijena paketa armature

    Vaš rezultat
    A rate per net tonne, and the package price
    Dokument
    Supplier quotation and labour rates
    U ERP-u
    Bill of Quantities, Markups
  5. Change

    Zadatak 5 · 50 min

    Revizija C: ponovno mjerenje izmjene

    Vaš rezultat
    The variation (priced change) for the new bar sizes
    Dokument
    Engineer's instruction EI 07, Revision C
    U ERP-u
    Variations

How a drawing becomes a price

Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.

Beam bars and links, in metres
Zadatak 1Cut lengthOutside dimensions, less what the bends take back, times the number of bars.
Slab bars and meshBeams
Zadatak 2Slab steelBars counted by spaces rounded up, plus one, a lap at each joint, mesh laid out sheet by sheet.
Overhead and profitNet tonnes at their rates
Zadatak 4Package priceNet tonnes times a rate built from supply, waste, cutting and fixing. One markup row on top.
Revision CPackage price
Zadatak 5VariationNew sizes go in, old sizes come out, both at the bill rates.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.